State: Odisha District: Puri Block: Sadar Gram Panchayat: Chalisibatia
Work Code: OD/369/3545/121067/409754/00013572 (Imp of Kanchi Harijan Sahi CC Road)
Project Category: Road
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Sadar Proposal Date: 15-07-2021
Date of Commencement: 08-10-2025 Date of Completion: 06-02-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: Rashmi Ranjan Khatua
Administrative Approval Details
Approval No.: OD/369/3545/121067/409754/00013572/AS
Technical Sanction Details
Technical Sanction No.: OD/369/3545/121067/409754/00013572/TS
Fund Sanction No.: 11088
Fund Sanction Amount (in Rs.): 300000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 21.86623296 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 21.86623296 Cum 1 21.86623296 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 21.86623296 Cum - - 2.29 50.0736734784 0.48 10.4957918208 0.96 20.9915836416 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 16.565328 Cum - - 3.23 53.50600944 0.45 7.4543976 - - 0.9 14.9087952 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 43.478604 Sqm - - - - - - - - - - 0.00267 0.11608787268 0.126 5.478304104
Total Qty 21.86623296 103.5796829184 17.9501894208 20.9915836416 14.9087952 0.11608787268 5.478304104
Rate Per Unit 583.89 600.588 806.71 2003.31 2414.93 58573.086 229.106
Total Amount 12767.474763014 62208.714604596 14480.597307654 42052.649425054 36003.696792336 6799.6249500427 1255.112340051
Total Material Amount (in Rs.): 175567.87018275