State: Odisha District: Cuttack Block: Baranga Gram Panchayat: Dadhapatna
Work Code: OD/350/3336/116936/907103/00016935 (Maint. & Imp. of Road with CC/ Gr-II Metalling from Station Bazar Level Crossing to Kanak Durga Temple)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Baranga Proposal Date: -
Date of Commencement: 05-06-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: Mettalling Road Project Type: Repair and Maintenance
Name of Executant: Santosh Kumar Patra
Administrative Approval Details
Approval No.: OD/350/3336/116936/907103/00016935/AS
Technical Sanction Details
Technical Sanction No.: OD/350/3336/116936/907103/00016935/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 186532
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM056 BRM104 BRM092 BRM044
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 23.099712768 Cum 3.23 74.61207224064 0.45 10.3948707456 0.9 20.7897414912 - - - - - -
2 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 12.63109188 Sqm - - - - - - 0.00267 0.0337250153196 0.126 1.59151757688 - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 1.3592064 Cum 2.29 3.112582656 0.48 0.652419072 - - - - - - 0.96 1.304838144
Total Qty 77.72465489664 11.0472898176 20.7897414912 0.0337250153196 1.59151757688 1.304838144
Rate Per Unit 563.767 417.99 2319.71 58573.086 229.106 1891.11
Total Amount 43818.595517114 4617.6566708586 48226.171234552 1975.3782226662 364.62622596867 2467.5924624998
Total Material Amount (in Rs.): 101470.02033366