State: Odisha District: Bargarh Block: Attabira Gram Panchayat: Godbhaga
Work Code: OD/347/3311/116349/380860/00030943 (Improvement of Gaon Kata,Godbhaga)
Project Category: Water Body
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Attabira Proposal Date: 30-01-2025
Date of Commencement: 09-12-2025 Date of Completion: -
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: Tank Project Type: Upgradation or Improvement
Name of Executant: Puspalata Behera
Administrative Approval Details
Approval No.: OD/347/3311/116349/380860/00030943/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3311/116349/380860/00030943/TS
Fund Sanction No.: 14036
Fund Sanction Amount (in Rs.): 300000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 17.94816 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 7.947776 Cum 1 7.947776 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 26.878464 Cum - - 2.29 61.55168256 0.48 12.90166272 0.96 25.80332544 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 17.0163 Cum - - 3.23 54.962649 0.45 7.657335 - - 0.9 15.31467 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 32.6952 Sqm - - - - - - - - - - 0.00267 0.087296184 0.126 4.1195952
Total Qty 7.947776 116.51433156 20.55899772 25.80332544 15.31467 0.087296184 4.1195952
Rate Per Unit 531.61 642.957 539.24 1549.69 1998.13 58573.086 229.106
Total Amount 4225.11719936 74913.705076823 11086.233930533 39987.155401114 30600.7015671 5113.2068929038 943.8239778912
Total Material Amount (in Rs.): 166869.94404572