State: Odisha District: Balangir Block: Turekela Gram Panchayat: Buromal
Work Code: OD/345/3297/116027/421208/00038032 (Repair & Maintenance of Primary School Kukudahad)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Turekela Proposal Date: -
Date of Commencement: - Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Primary School Building
Project Sub-Category: Elementary School Project Type: Repair and Maintenance
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.: 34989
Fund Sanction Amount (in Rs.): 266878
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM120 BRMMR0027 BRM340 BRM028 BRM064 BRM056 BRMMR0038 BRM140 BRM253 BRM255 BRM137 BRM141 BRM045
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 52.153421625 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Dismantling (AR1613) :.Removing old lime or cement plaster - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 19.50963 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
3 Dismantling (AR1621) :.Removing old grading plaster from roof - Removing old grading plaster from roof slab, cleaning the surface,lowering and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 62.430816 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
4 Dismantling (AR1623) :.Dismantling and removing cement concrete - Dismantling and removing cement concrete including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 5.245793388 Cum - - - - - - - - - - - - - - - - - - - - - - - - - -
5 Flooring (AR0816c) :.Fixing Kota Tiles of minimum 16 mm thick Up to 0.10 Sqm. in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 - Fixing Kota Tiles of minimum 16 mm thick Up to 0.10 Sqm. in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the kota tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. 52.153421625 Sqm 1 52.153421625 1 52.153421625 0.2737 14.274391498762 0.013 0.677994481125 - - - - - - - - - - - - - - - - - -
6 Concrete (AR0318) :.4cm thick grading concrete (1:2:4) on roof slab with 12mm size hard granite chips (Crusher Broken) - 4cm thick grading concrete (1:2:4) on roof slab with 12mm size hard granite chips (Crusher Broken) including hoisting and laying in position compacting and curing for the proper period with cost conveyance, royalty, taxes of all materials, labor and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (Old Work) 62.430816 Sqm - - - - 0.1287 8.0348460192 0.018 1.123754688 0.018 1.123754688 0.018 1.123754688 - - - - - - - - - - - - - -
7 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 177.630536 Sqm - - - - - - - - - - - - 0.8 142.1044288 - - - - - - - - - - - -
8 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 19.50963 Sqm - - - - 0.043 0.83891409 0.018 0.35117334 - - - - - - - - - - - - - - - - - -
9 Painting(AR0920) :.Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 177.630536 Sqm - - - - - - - - - - - - - - 0.125 22.203817 - - - - - - - - - -
10 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 177.630536 Sqm - - - - - - - - - - - - - - - - 0.084 14.920965024 - - - - - - - -
11 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 289.950263 Sqm - - - - - - - - - - - - - - - - 0.090322580645161 26.189056012903 0.125 36.243782875 - - - - - -
12 Painting(AR0901b) :.Priming one coat in inner surface with primer of approved quality over iron work. - Priming one coat in inner surface with primer of approved quality over iron work including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 79.0140015 Sqm - - - - - - - - - - - - - - - - - - - - 0.054 4.266756081 - - - -
13 Painting(AR0903i) :.Painting two coats of enamel paint in outer surface paint (outer surface) - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 79.0140015 Sqm - - - - - - - - - - - - - - - - - - - - - - 0.125 9.8767501875 - -
14 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 4.682784612 Cum - - - - 2.29 10.72357676148 0.48 2.24773661376 - - - - - - - - - - - - - - - - 0.96 4.49547322752
15 Plastering (AR1027) :.6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 33.456692875 Sqm - - - - 0.0372 1.24458897495 0.0075 0.2509251965625 - - - - - - - - - - - - - - - - - -
Total Qty 52.153421625 52.153421625 35.116317344392 4.6515843194475 1.123754688 1.123754688 142.1044288 22.203817 41.110021036903 36.243782875 4.266756081 9.8767501875 4.49547322752
Rate Per Unit 421.6011111 8.5 528.967 782.55 1139.23 1685.65 30 249.58787 159.27787 195.03787 142.94787 205.58787 1076.39
Total Amount 21987.940504767 443.3040838125 18575.373036711 3640.0973091836 1280.2150532102 1894.2570898272 4263.132864 5541.8033908998 6547.9165864131 7068.9102126825 609.9236935885 2030.5400335702 4838.8824273703
Total Material Amount (in Rs.): 78722.296286036