State: Odisha District: Sundargarh Block: Rajgangpur Gram Panchayat: Garvana
Work Code: OD/373/3586/275334/384217/00039189 (CONSTRUCTION OF BOUNDARY WALL AT GARVANA PADHA HOUSE )
Project Category: Other Infrastructure
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Rajgangpur Proposal Date: -
Date of Commencement: 23-09-2025 Date of Completion: 27-10-2025
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD
Project Sub-Category: Boundary Wall Project Type: New Work
Name of Executant: RUPAK KUMAT PATEL
Administrative Approval Details
Approval No.: OD/373/3586/275334/384217/00039189/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3586/275334/384217/00039189/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 390000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM005 BRMMR0025 BRM143 BRM031
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 30.6 Cum - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 6.12 Cum 1 6.12 - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 6.12 Cum - - 2.29 14.0148 0.48 2.9376 0.96 5.8752 - - - - - - - -
4 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 287.28 Sqm - - 0.043 12.35304 0.018 5.17104 - - - - - - - - - -
5 Masonry Brick Work (AR0603b) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 15.504 Cum - - 0.672 10.418688 0.28 4.34112 - - 350 5426.4 - - - - - -
6 Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 31.5567 Cum - - 0.672 21.2061024 0.28 8.835876 - - 350 11044.845 1 31.5567 - - - -
7 Painting(AR0918c) :.Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work (Outside) - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 287.28 Sqm - - 0.010763440860215 3.0921212903226 - - - - - - - - 0.25 71.82 - -
8 Plastering (AR1033) :.White washing two coats with stone lime in any surface - White washing two coats with stone lime in any surface including all costs of labour, coaltar and brushes required for the work etc. complete and as per direction of Engineer-in-charge. 287.28 Sqm - - - - - - - - - - - - - - 1.149247311828 330.15576774194
Total Qty 6.12 61.084751690323 21.285636 5.8752 16471.245 31.5567 71.82 330.15576774194
Rate Per Unit 517.21 588.237 522.15 1570.72 6.1539 33 48.07787 21.88
Total Amount 3165.3252 35932.31108006 11114.2948374 9228.294144 101362.3946055 1041.3711 3452.9526234 7223.8081981935
Total Material Amount (in Rs.): 172520.75178855