State: Odisha District: Jagatsinghpur Block: Tirtol Gram Panchayat: Tulanga
Work Code: OD/355/3393/118234/397779/00040193 (REPAIRING OF CC ROAD FROM TAMAPADA BASANTA SWAIN HOUSE TO SAHANI THAKURANI TEMPLE, VILLAGE TAMAPADA.)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Tirtol Proposal Date: 07-12-2024
Date of Commencement: 18-10-2025 Date of Completion: 02-12-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: Repair and Maintenance
Name of Executant: MONALISA MALLICK
Administrative Approval Details
Approval No.: OD/355/3393/118234/397779/00040193/AS
Technical Sanction Details
Technical Sanction No.: OD/355/3393/118234/397779/00040193/TS
Fund Sanction No.: 30636
Fund Sanction Amount (in Rs.): 143788
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM045 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 1.344 Cum 2.29 3.07776 0.48 0.64512 0.96 1.29024 - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.87808 Cum 3.23 48.0561984 0.45 6.695136 - - 0.9 13.390272 - - - -
3 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 6.72 Sqm - - - - - - - - 0.00267 0.0179424 0.126 0.84672
Total Qty 51.1339584 7.340256 1.29024 13.390272 0.0179424 0.84672
Rate Per Unit 631.162 738.32 2345.94 2994.53 58620.646 276.666
Total Amount 32273.811451661 5419.45780992 3026.8256256 40097.57121216 1051.7950787904 234.25863552
Total Material Amount (in Rs.): 82103.719813651