| State: Odisha |
District: Bargarh |
Block: Sohella |
Gram Panchayat: Tungibandhali |
Work Code: OD/347/3321/116580/380299/00040430 (IMPROVEMENT OF ROAD FROM TUNGIBANDHALI TO MATHURAPALI )
Project Category: Road
| Financial Year: 2025-26 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Sohella |
Proposal Date: - |
| Date of Commencement: 03-12-2025 |
Date of Completion: - |
| Scheme Name: 5th SFC Grant in Aid |
Scheme Component Name: Maintenance and improvement of Road infrastructure |
| Project Sub-Category: Mettalling Road |
Project Type: Upgradation or Improvement |
| Name of Executant: JAYRAM BAG |
|
Administrative Approval Details
Approval No.: OD/347/3321/116580/380299/00040430/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3321/116580/380299/00040430/TS
Fund Sanction No.: 29133
Fund Sanction Amount (in Rs.): 1000000
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM041 |
BRM025 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. |
233.472 |
Cum |
1 |
233.472 |
0.3 |
70.0416 |
| 2 |
Road Work (AR1307) :.Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. |
420.48 |
Cum |
- |
- |
1.28 |
538.2144 |
| Total Qty |
233.472 |
608.256 |
| Rate Per Unit |
1009.68 |
338.09 |
| Total Amount |
235732.00896 |
205645.27104 |
Total Material Amount (in Rs.): 441377.28