State: Odisha District: Nabarangpur Block: Dabugam Gram Panchayat: Dabugam
Work Code: OD/366/3514/120436/427645/00050562 (Renovation Tank at Dumuniguda Upper Sahi under Dabugam GP)
Project Category: Water Body
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Dabugam Proposal Date: -
Date of Commencement: 10-10-2025 Date of Completion: 04-11-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Tank Project Type: Renovation or Rejuvenation
Name of Executant: Abinash Nayak
Administrative Approval Details
Approval No.: OD/366/3514/120436/427645/00050562/AS
Technical Sanction Details
Technical Sanction No.: OD/366/3514/120436/427645/00050562/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 200000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM057 BRM143 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 21.1125 Cum - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 18.1335 Cum 1 18.1335 - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 24.59025 Cum - - 2.29 56.3116725 0.48 11.80332 0.96 23.60664 - - - - - - - -
4 Concrete (AR0307a) :.Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.3678 Cum - - 3.23 10.877994 0.45 1.51551 - - 0.9 3.03102 - - - - - -
5 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 76.4825 Sqm - - 0.0358 2.7380735 0.015 1.1472375 - - - - - - - - - -
6 Painting(AR0918c) :.Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work (Outside) - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 76.4825 Sqm - - 0.010763440860215 0.8232148655914 - - - - - - 0.25 19.120625 - - - -
7 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 40.87 Sqm - - - - - - - - - - - - 0.00267 0.1091229 0.126 5.14962
Total Qty 18.1335 70.750954865591 14.4660675 23.60664 3.03102 19.120625 0.1091229 5.14962
Rate Per Unit 347.95 573.227 417.24 1466.56 1556.5 48.07787 58573.086 229.106
Total Amount 6309.551325 40556.357604738 6035.8220037 34620.5539584 4717.78263 919.27892306875 6391.6650062694 1179.80883972
Total Material Amount (in Rs.): 100730.8202909