State: Odisha District: Kendujhar Block: Joda Gram Panchayat: Bolani
Work Code: OD/361/3451/119441/385276/00054228 (CONST. OF CC ROAD FROM MURALI BEHERA HOUSE TO BABAJI SHOP HOUSE)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Joda Proposal Date: 11-09-2024
Date of Commencement: 20-09-2025 Date of Completion: -
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: JYOTIRANJAN PRADHAN
Administrative Approval Details
Approval No.: OD/361/3451/119441/385276/00054228/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3451/119441/385276/00054228/TS
Fund Sanction No.: 5003
Fund Sanction Amount (in Rs.): 800000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0103aa) :.Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume in foundation and plinth within 50m. Initial lead and 1.5m - Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume in foundation and plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layer not exceeding 0.3m in depth and as per specification approved by the department 9.045 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 33.6675 Cum 1 33.6675 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 57.4525 Cum - - 2.29 131.566225 0.48 27.5772 0.96 55.1544 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 35.175 Cum - - 3.23 113.61525 0.45 15.82875 - - 0.9 31.6575 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 87.1 Sqm - - - - - - - - - - 0.00267 0.232557 0.126 10.9746
Total Qty 33.6675 245.181475 43.40595 55.1544 31.6575 0.232557 10.9746
Rate Per Unit 1652.91 616.087 1662.91 2225.16 2599.91 58573.086 229.106
Total Amount 55649.347425 151053.11938832 72180.1883145 122727.364704 82306.650825 13621.581160902 2514.3467076
Total Material Amount (in Rs.): 500052.59852533