State: Odisha District: Gajapati Block: Rayagad Gram Panchayat: Dambala
Work Code: OD/353/3363/117548/414752/00061008 (Improvement of Tank at Mandalsahi near Ashram School)
Project Category: Water Body
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Rayagad Proposal Date: -
Date of Commencement: 24-10-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Tank Project Type: Upgradation or Improvement
Name of Executant: Janemejay Mohanta
Administrative Approval Details
Approval No.: OD/353/3363/117548/414752/00061008/AS
Technical Sanction Details
Technical Sanction No.: OD/353/3363/117548/414752/00061008/TS
Fund Sanction No.: 3971
Fund Sanction Amount (in Rs.): 300000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0103aa) :.Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume in foundation and plinth within 50m. Initial lead and 1.5m - Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume in foundation and plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layer not exceeding 0.3m in depth and as per specification approved by the department 14.58 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.55 Cum 1 5.55 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 34.3 Cum - - 2.29 78.547 0.48 16.464 0.96 32.928 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 1.835 Cum - - 3.23 5.92705 0.45 0.82575 - - 0.9 1.6515 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 124.75 Sqm - - - - - - - - - - 0.00267 0.3330825 0.126 15.7185
6 Plastering (AR1008) :.20mm thick cement Plaster in CM (1:6) over brick work in inside. - 20mm thick cement Plaster in CM (1:6) for stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 22.05 Sqm - - 0.057 1.25685 0.021 0.46305 - - - - - - - -
Total Qty 5.55 85.7309 17.7528 32.928 1.6515 0.3330825 15.7185
Rate Per Unit 1025.85 807.512 1030.79 1949.16 2350.53 58620.646 276.666
Total Amount 5693.4675 69228.7305208 18299.408712 64181.94048 3881.900295 19525.511321295 4348.774521
Total Material Amount (in Rs.): 185159.73335009