State: Odisha District: Sundargarh Block: Kutra Gram Panchayat: Rajabasa
Work Code: OD/373/3581/121655/384161/00061045 (CONST. OF CC DRAIN AT TUNGRIPADA RAJABASA)
Project Category: CD Work
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Kutra Proposal Date: -
Date of Commencement: 01-11-2025 Date of Completion: -
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: Drain Masonry or Cement Concrete Project Type: New Work
Name of Executant: REENA PRATIMA KUJUR
Administrative Approval Details
Approval No.: OD/373/3581/121655/384161/00061045/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3581/121655/384161/00061045/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 202038
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 46.98 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 7.83 Cum 1 7.83 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 7.83 Cum - - 2.29 17.9307 0.48 3.7584 0.96 7.5168 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.21 Cum - - 3.23 45.8983 0.45 6.3945 - - 0.9 12.789 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 139.2 Sqm - - - - - - - - - - 0.00267 0.371664 0.126 17.5392
Total Qty 7.83 63.829 10.1529 7.5168 12.789 0.371664 17.5392
Rate Per Unit 478.15 582.292 483.09 1570.72 1972.09 58573.086 229.106
Total Amount 3743.9145 37167.116068 4904.764461 11806.788096 25221.05901 21769.507435104 4018.3359552
Total Material Amount (in Rs.): 108631.4855253