State: Odisha District: Kandhamal Block: K.Nuagan Gram Panchayat: Letingia
Work Code: OD/359/3426/275212/416886/00063738 (Construction of CC road from Bandangia chhaka to Gunjinata at Letingia GP )
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, K.Nuagan Proposal Date: 28-05-2025
Date of Commencement: 06-12-2025 Date of Completion: 05-01-2026
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: Mettalling Road Project Type: New Work
Name of Executant: Priyanka Patro
Administrative Approval Details
Approval No.: OD/359/3426/275212/416886/00063738/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3426/275212/416886/00063738/TS
Fund Sanction No.: 200000
Fund Sanction Amount (in Rs.): 200000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM056 BRM029 BRM045 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.475 Cum 3.23 37.06425 0.45 5.16375 0.9 10.3275 - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.5 Cum - - - - - - 1 13.5 - - - - - -
3 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.6 Cum - - - - - - - - - - - - - -
4 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 17.1 Cum 2.29 39.159 0.48 8.208 - - - - 0.96 16.416 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 18 Sqm - - - - - - - - - - 0.00267 0.04806 0.126 2.268
Total Qty 76.22325 13.37175 10.3275 13.5 16.416 0.04806 2.268
Rate Per Unit 608.852 678.39 2442.53 476.21 1388.87 58573.086 229.106
Total Amount 46408.678209 9071.2614825 25225.228575 6428.835 22799.68992 2815.02251316 519.612408
Total Material Amount (in Rs.): 113268.32810766