State: Odisha District: Ganjam Block: Surada Gram Panchayat: Gochha
Work Code: OD/354/3385/118027/410808/00064281 (Reno of Kandhunidevi Mandir at Dabik)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Surada Proposal Date: -
Date of Commencement: 04-12-2025 Date of Completion: -
Scheme Name: Chief Minister Special Assistant Scheme Component Name: Chief Minister Special Assistance (CM-SA)
Project Sub-Category: Community Centre Project Type: Renovation or Rejuvenation
Name of Executant: Narahari Mundia
Administrative Approval Details
Approval No.: OD/354/3385/118027/410808/00064281/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3385/118027/410808/00064281/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 450000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM079 BRM056 BRM060 BRM052 BRM162 BRM341 BRM104 BRM092 BRM094 BRM084 BRMMR0025 BRM002 BRM057 BRM142 BRM253 BRM255 BRM140 BRM137 BRM141
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 7.328604 Cum - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 4.32054 Cum 1 4.32054 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 3.96039 Cum - - 2.29 9.0692931 0.48 1.9009872 0.96 3.8019744 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 Masonry Stone Work (AR0717) :.Laterite stone masonry - Laterite stone masonry in cement mortar (1:6) in foundation and plinth cost conveyance, royalty, taxes of all materials, labor, required for the work, etc. complete and as per direction of the Engineer-in-charge. 6.078072 Cum - - 0.572 3.476657184 0.24 1.45873728 - - 1 6.078072 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.553392 Cum - - 3.23 1.78745616 0.45 0.2490264 - - - - 0.9 0.4980528 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
6 R.C.C. Work (AR0404A) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 3.284746 Cum - - 3.4733 11.4089082818 0.45 1.4781357 - - - - - - 0.36 1.18250856 0.54 1.77376284 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
7 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 3.3 Qntl - - - - - - - - - - - - - - - - 0.8 2.64 1.05 3.465 - - - - - - - - - - - - - - - - - - - - - - - - - -
8 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 6.6332 Sqm - - - - - - - - - - - - - - - - - - - - 0.00267 0.017710644 0.126 0.8357832 - - - - - - - - - - - - - - - - - - - - - -
9 R.C.C. Work (AR0410e) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm 4.326 Sqm - - - - - - - - - - - - - - - - - - - - 0.0052948717948718 0.022905615384615 - - 0.26923076923077 1.1646923076923 - - - - - - - - - - - - - - - - - - - -
10 R.C.C. Work (AR0410d) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 2.2638 Sqm - - - - - - - - - - - - - - - - - - - - 0.0051904761904762 0.0117502 - - - - 0.55238095238095 1.25048 - - - - - - - - - - - - - - - - - -
11 R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 19.6618 Sqm - - - - - - - - - - - - - - - - - - - - 0.0050222222222222 0.098745928888889 - - - - 0.62222222222222 12.234008888889 - - - - - - - - - - - - - - - - - -
12 Masonry Brick Work (AR0603ei) :.C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 14.133689 Cum - - 0.672 9.497839008 0.28 3.95743292 - - - - - - - - - - - - - - - - - - - - - - 1 14.133689 400 5653.4756 - - - - - - - - - - - - - -
13 Flooring (AR0802ii) :.2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 10.8003 Sqm - - 0.0858 0.92666574 0.012 0.1296036 - - - - - - - - - - - - - - - - - - - - - - - - - - 0.023 0.2484069 - - - - - - - - - - - -
14 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 105.0323 Sqm - - 0.043 4.5163889 0.018 1.8905814 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
15 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 64.3595 Sqm - - 0.0358 2.3040701 0.015 0.9653925 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
16 Painting(AR0922b) :.Finishing wall surface with two coats with distemper of approved shades above one coat waterbound Primer on new work (Inside) - Finishing wall surface with two coats with distemper of approved shades above one coat waterbound Primer for new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 67.8266 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.25 16.95665 0.084 5.6974344 - - - - - - - -
17 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 64.3595 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.090322580645161 5.8131161290323 0.125 8.0449375 - - - - - -
18 Painting(AR0917h) :.Finishing wall with one coat weather coat paint of approved shade including one coat of water bound primer in the outer surface of old work (Outside) - Finishing wall with one coat weather coat paint of approved shade including one coat of water bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 246.7679 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.090322580645161 22.288713548387 0.075 18.5075925 - - - - - -
19 Painting(AR0919b) :.Finishing wall surface with One Coat with plastic emulsion paint of approved shades above one coat water bound Primer on old work (Inside) - Finishing wall surface with One Coat with plastic emulsion paint of approved shades above one coat waterbound Primer on old work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge..(Inside) 241.2719 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.084 20.2668396 - - 0.075 18.0953925 - - - -
20 Painting(AR0920) :.Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 96 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.125 12 - - - -
21 Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 1.00330006 Qntl - - - - - - - - - - - - - - - - - - 1 1.00330006 - - - - - - - - - - - - - - - - - - - - - - - - - -
22 Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 24.131025 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.054 1.30307535 0.125 3.016378125
Total Qty 4.32054 42.9872784738 12.029897 3.8019744 6.078072 0.4980528 1.18250856 1.77376284 2.64 4.46830006 0.1511123882735 0.8357832 1.1646923076923 13.484488888889 14.133689 5653.4756 0.2484069 16.95665 54.066103677419 26.55253 30.0953925 1.30307535 3.016378125
Rate Per Unit 403.97 598.442 407.34 1401.46 1059.58 1802.83 1813.98 1788.5 90.1 6223.172 58573.086 229.106 240.106 250.166 33 4.92297 1476.21 70.34787 159.27787 195.03787 249.58787 142.94787 205.58787
Total Amount 1745.3685438 25725.392904418 4900.25824398 5328.315042624 6440.20352976 897.904529424 2145.0468776688 3172.37483934 237.864 27806.99982099 8851.1189140094 191.4829458192 279.64961123077 3373.3606473778 466.411737 27831.890774532 366.700749849 1192.8642098355 8611.5338329385 5178.7488943111 7511.444910889 186.271845732 620.13075383334
Total Material Amount (in Rs.): 143061.33815936