| State: Odisha |
District: Khordha |
Block: Bhubaneswar |
Gram Panchayat: Dhauli |
Work Code: OD/362/3460/119604/407760/00085859 (RETESTINGTENDER27-01-2000)
Project Category: Building
| Financial Year: 2025-26 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Bhubaneswar |
Proposal Date: - |
| Date of Commencement: - |
Date of Completion: - |
| Scheme Name: 5th SFC Grant in Aid |
Scheme Component Name: Street Light |
| Project Sub-Category: GP Bhawan |
Project Type: New Work |
| Name of Executant: |
|
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 3000000
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM340 |
BRM028 |
BRM044 |
BRM104 |
BRM092 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0103a1) :.Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m - Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per specification approved by the dept. |
88.49 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. |
434.946048 |
Cum |
2.29 |
996.02644992 |
0.48 |
208.77410304 |
0.96 |
417.54820608 |
- |
- |
- |
- |
| 3 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
240.804576 |
Sqm |
- |
- |
- |
- |
- |
- |
0.00267 |
0.64294821792 |
0.126 |
30.341376576 |
| Total Qty |
996.02644992 |
208.77410304 |
417.54820608 |
0.64294821792 |
30.341376576 |
| Rate Per Unit |
569.387 |
338.59 |
1271.26 |
58573.086 |
229.106 |
| Total Amount |
567124.5122406 |
70688.823548314 |
530812.33246126 |
37659.461261775 |
6951.3914218211 |
Total Material Amount (in Rs.): 1213236.5209338