State: Odisha District: Kandhamal Block: Phiringia Gram Panchayat: Balandapada
Work Code: OD/359/3429/118957/415124/00070643 (Construction of GP Facility center at Balandapada GP)
Project Category: Building
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Phiringia Proposal Date: -
Date of Commencement: 07-01-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Provision of Facilities at GP Head Quarter
Project Sub-Category: GP Facility Centre Project Type: New Work
Name of Executant: BIBHUDANANDA BISWAL
Administrative Approval Details
Approval No.: OD/359/3429/118957/415124/00070643/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3429/118957/415124/00070643/TS
Fund Sanction No.: 22566
Fund Sanction Amount (in Rs.): 1000000
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM060 BRM052 BRM341 BRM104 BRM092 BRM094 BRM084 BRM005 BRM131 BRM129 BRM253 BRM140 BRM137 BRM141
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 35.11849536 Cum - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.55858784 Cum 1 5.55858784 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 20.338631845642 Cum - - 2.29 46.57546692652 0.48 9.7625432859082 0.96 19.525086571816 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 R.C.C. Work (AR0404A) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 18.954430546083 Cum - - 3.4733 65.83442361571 0.45 8.5294937457373 - - 0.36 6.8235949965899 0.54 10.235392494885 - - - - - - - - - - - - - - - - - - - - - - - -
5 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 17.61 Qntl - - - - - - - - - - - - 1.05 18.4905 - - - - - - - - - - - - - - - - - - - - - -
6 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 51.25179801 Sqm - - - - - - - - - - - - - - 0.00267 0.1368423006867 0.000614 0.03146860397814 - - - - - - - - - - - - - - - - - -
7 R.C.C. Work (AR0410e) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm 11.93710647 Sqm - - - - - - - - - - - - - - 0.0052948717948718 0.063205448360385 - - 0.0035384615384615 0.042238992124615 - - - - - - - - - - - - - - - -
8 R.C.C. Work (AR0410d) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 54.1162576284 Sqm - - - - - - - - - - - - - - 0.0051904761904762 0.28088914673789 - - - - 0.0056666666666667 0.3066587932276 - - - - - - - - - - - - - -
9 R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 56.0619530283 Sqm - - - - - - - - - - - - - - 0.0050222222222222 0.28155558631991 - - - - 0.0076666666666667 0.4298083065503 - - - - - - - - - - - - - -
10 Masonry Brick Work (AR0603b) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 5.27599537896 Cum - - 0.672 3.5454688946611 0.28 1.4772787061088 - - - - - - - - - - - - - - - - 350 1846.598382636 - - - - - - - - - - - -
11 Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 20.949936708 Cum - - 0.672 14.078357467776 0.28 5.86598227824 - - - - - - - - - - - - - - - - 350 7332.4778478 - - - - - - - - - - - -
12 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 76.2269115 Sqm - - 0.0358 2.7289234317 0.015 1.1434036725 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
13 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 126.22916416 Sqm - - 0.043 5.42785405888 0.018 2.27212495488 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
14 Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 35.9160954134 Sqm - - 0.1375 4.9384631193425 0.015 0.538741431201 - - - - - - - - - - - - - - - - - - 1 35.9160954134 - - - - - - - - - -
15 Flooring (AR0817b) :.Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. 24.39261168 Sqm - - 0.1375 3.353984106 0.015 0.3658891752 - - - - - - - - - - - - - - - - - - - - 1 24.39261168 - - - - - - - -
16 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 154.95941691 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.084 13.01659102044 - - - - - -
17 Painting(AR0901di) :.Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces(outer surface ) - Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 78.781744 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.090322580645161 7.1157704258065 - - - - - -
18 Painting(AR0920b) :.Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat waterbound Primer on new work (Inside) - Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat waterbound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 238.87683875 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.084 20.065654455 0.125 29.85960484375 - - - -
19 Plastering (AR1026) :.6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces (inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 50.93406975 Sqm - - 0.0271 1.380313290225 0.0075 0.382005523125 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
20 Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 30.12379775 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.054 1.6266850785 0.125 3.76547471875
21 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 133.38826934 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Total Qty 5.55858784 147.86325491081 30.3374627729 19.525086571816 6.8235949965899 10.235392494885 18.4905 0.76249248210488 0.03146860397814 0.042238992124615 0.7364670997779 9179.076230436 35.9160954134 24.39261168 40.198015901246 29.85960484375 1.6266850785 3.76547471875
Rate Per Unit 40.25 0 40.25 149.5 149.5 149.5 0 0 0 0 0 0 0 0 0 0 0 0
Total Amount 223.73316056 0 1221.0828766092 2919.0004424865 1020.1274519902 1530.1911779853 0 0 0 0 0 0 0 0 0 0 0 0
Total Royalty Amount (in Rs.): 6914.1351096312