State: Odisha District: Kandhamal Block: Tumudibandh Gram Panchayat: Tumudibandh
Work Code: OD/359/3433/119018/416964/00072307 (Construction of GP Godown at Tumudibandha)
Project Category: Building
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Tumudibandh Proposal Date: 24-08-2021
Date of Commencement: 21-01-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Creation of Capital Asset for Revenue Generation
Project Sub-Category: Godown Project Type: New Work
Name of Executant: Sunil
Administrative Approval Details
Approval No.: OD/359/3433/119018/416964/00072307/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3433/119018/416964/00072307/TS
Fund Sanction No.: 14
Fund Sanction Amount (in Rs.): 1000000
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM034 BRM060 BRM052 BRM104 BRM092 BRM084 BRM094 BRM341 BRM005 BRM174 BRM131 BRM143 BRM141 BRM138
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 32.9926116 Cum - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 25.11770952 Cum 1 25.11770952 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
3 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 11.55396232 Cum - - 2.29 26.4585737128 0.48 5.5459019136 0.96 11.0918038272 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 Masonry Stone Work (AR0703) :.Random rubble H.G. stone of masonry. - Random rubble H.G. stone of size not less than 0.0025 cum stacked masonry in cement mortar (1:6) in foundation and plinth including watering, curing for seven days with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.84978086016 Cum - - 0.8151 11.288956379116 0.34 4.7089254924544 - - 1 13.84978086016 - - - - - - - - - - - - - - - - - - - - - - - - - -
5 R.C.C. Work (AR0404Aa) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) 5.66336 Cum - - 3.4733 19.670548288 0.45 2.548512 - - - - 0.36 2.0388096 0.54 3.0582144 0.004005 0.0226817568 0.000921 0.00521595456 - - - - - - - - - - - - - - - - - -
6 R.C.C. Work (AR0404Ab) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) 1.8209798975872 Cum - - 3.4733 6.3248094782896 0.45 0.81944095391424 - - - - 0.36 0.65555276313139 0.54 0.98332914469709 0.01335 0.024310081632789 0.00307 0.0055904082855927 - - - - - - - - - - - - - - - - - -
7 R.C.C. Work (AR0404Ac) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 4.92022381168 Cum - - 3.4733 17.089413365108 0.45 2.214100715256 - - - - 0.36 1.7712805722048 0.54 2.6569208583072 0.041529 0.20433197467526 - - 0.045339 0.22307802739776 - - - - - - - - - - - - - - - -
8 R.C.C. Work (AR0404Ad) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) 1.35894022208 Cum - - 3.4733 4.7200070733505 0.45 0.611523099936 - - - - 0.36 0.4892184799488 0.54 0.7338277199232 0.0741335 0.10074299495357 - - - - 0.049542 0.067324616482287 - - - - - - - - - - - - - -
9 R.C.C. Work (AR0404Ag) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 11.706777442483 Cum - - 3.4733 40.661150090976 0.45 5.2680498491174 - - - - 0.36 4.2144398792939 0.54 6.3216598189408 0.0502172 0.58788158418466 - - 0.076659 0.8974298519633 - - - - - - - - - - - - - - - -
10 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 25.47 Qntl - - - - - - - - - - - - - - - - - - - - - - 1.05 26.7435 - - - - - - - - - - - -
11 Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 21.54068320544 Cum - - 0.672 14.475339114056 0.28 6.0313912975232 - - - - - - - - - - - - - - - - - - 350 7539.239121904 - - - - - - - - - -
12 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 112.846951525 Sqm - - 0.0358 4.039920864595 0.015 1.692704272875 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
13 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 106.641031125 Sqm - - 0.043 4.585564338375 0.018 1.91953856025 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
14 Plastering (AR1017) :.20mm thick cement Plaster in CM (1:4) over masonry work in inside. - 20mm thick cement Plaster in CM (1:4) over stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 90.2407623417 Sqm - - 0.0744 6.7139127182225 0.021 1.8950560091757 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
15 Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 55.7418 Sqm - - 0.1074 5.98666932 0.021 1.1705778 - - - - - - - - - - - - - - - - - - - - 0.0076 0.42363768 1 55.7418 - - - - - -
16 Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 5.8064375 Sqm - - 0.1375 0.79838515625 0.015 0.0870965625 - - - - - - - - - - - - - - - - - - - - - - 1 5.8064375 - - - - - -
17 Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 4.29 Qntl - - - - - - - - - - - - - - - - - - - - - - 1 4.29 - - - - - - - - - - - -
18 Painting(AR0918c) :.Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work (Outside) - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 275.22978265 Sqm - - 0.010763440860215 2.9624194885231 - - - - - - - - - - - - - - - - - - - - - - - - - - 0.25 68.8074456625 - - - -
19 Painting(AR0903a) :.Painting two coats of enamel paint with a coat of wood primer in inner surface paint (Inside) - Painting two coats of enamel paint with a coat of wood primer in inner surface paint including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Inside) 28.3063828125 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.125 3.5382978515625 0.075 2.1229787109375
Total Qty 25.11770952 165.77566938766 34.512818526602 11.0918038272 13.84978086016 9.1693012945789 13.753951941868 0.93994839224627 0.010806362845593 1.1205078793611 0.067324616482287 31.0335 7539.239121904 0.42363768 61.5482375 68.8074456625 3.5382978515625 2.1229787109375
Rate Per Unit 40.25 0 40.25 149.5 149.5 149.5 149.5 0 0 0 0 0 0 0 0 0 0 0
Total Amount 1010.98780818 0 1389.1409456957 1658.2246721664 2070.5422385939 1370.8105435395 2056.2158153093 0 0 0 0 0 0 0 0 0 0 0
Total Royalty Amount (in Rs.): 9555.9220234849