| 1 |
Odisha |
Kendrapara |
Marsaghai |
Kuhudi |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road at Nambera Kanipada Mallik Sahi Road, vill- Kanipada |
59 days |
Forward Pending |
| 2 |
Odisha |
Dhenkanal |
Hindol |
Chitalpur |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Tikan Pal House to Sudhakar Pal Land |
108 days |
Forward Pending |
| 3 |
Odisha |
Dhenkanal |
Hindol |
Kukuta |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Ganeswar House to Majhi Harizan Sahi |
108 days |
Forward Pending |
| 4 |
Odisha |
Dhenkanal |
Hindol |
Ranjagol |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Sanahindol Harizansahi |
108 days |
Forward Pending |
| 5 |
Odisha |
Dhenkanal |
Hindol |
Asarada |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Govinda Sahu House to Ramachandra Sahu Khala Barsing Munda Sahi |
108 days |
Forward Pending |
| 6 |
Odisha |
Dhenkanal |
Hindol |
Thokar |
Sri Siddharth Sankar Swain |
Director PR |
Construction CC Road at Ganduragadi to Chumuki House |
108 days |
Forward Pending |
| 7 |
Odisha |
Dhenkanal |
Hindol |
Karanda |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Mahima Tungi to Jagadish Pradhan House Karanda Sanasahi |
108 days |
Forward Pending |
| 8 |
Odisha |
Dhenkanal |
Hindol |
Giridhar Prasad |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Rabi ROut House to Chandramani Naik House to Khandatiri Joragadia Sahi |
108 days |
Forward Pending |
| 9 |
Odisha |
Dhenkanal |
Hindol |
Babandha |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Main Road to Mandap Sahi Bedapada |
108 days |
Forward Pending |
| 10 |
Odisha |
Dhenkanal |
Hindol |
Kutunia |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Kharidali Thakuri Sahi |
108 days |
Forward Pending |
| 11 |
Odisha |
Dhenkanal |
Hindol |
Bampa |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at RD Road to Sukadev Majhi House |
108 days |
Forward Pending |
| 12 |
Odisha |
Dhenkanal |
Hindol |
Hatura |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Hatura Samsana to Mangala Mandir Road |
108 days |
Forward Pending |
| 13 |
Odisha |
Dhenkanal |
Hindol |
Kansara |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Dolamandap to Gopal Sahi Road |
108 days |
Forward Pending |
| 14 |
Odisha |
Dhenkanal |
Hindol |
Kantamila |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Harizansahi to AWC Center Kantamila Harizansahi |
108 days |
Forward Pending |
| 15 |
Odisha |
Dhenkanal |
Hindol |
Baunsa Pokhari |
Sri Siddharth Sankar Swain |
Director PR |
Construction of Medical CC Road at Baunsapokhari |
108 days |
Forward Pending |
| 16 |
Odisha |
Dhenkanal |
Hindol |
Mahalunda |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from PWD Road to Mahalunda Hatasahi |
108 days |
Forward Pending |
| 17 |
Odisha |
Dhenkanal |
Hindol |
Patala |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Tulasibani Siva Mandir |
108 days |
Forward Pending |
| 18 |
Odisha |
Dhenkanal |
Hindol |
Kantimili |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Kantimili Talasahi to Khalamala |
108 days |
Forward Pending |
| 19 |
Odisha |
Dhenkanal |
Hindol |
Kadala |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Gayatri House to Benipathar |
108 days |
Forward Pending |
| 20 |
Odisha |
Dhenkanal |
Hindol |
Paika Purunakot |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from PPKote Talasahi Sankhapadia to Lingara |
108 days |
Forward Pending |
| 21 |
Odisha |
Dhenkanal |
Hindol |
Galapada |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Ganeswar House to Telighana Jhadabandha |
108 days |
Forward Pending |
| 22 |
Odisha |
Dhenkanal |
Hindol |
Nuagan |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Brahmana PPkote RD Road to Suresh Naik House |
108 days |
Forward Pending |
| 23 |
Odisha |
Dhenkanal |
Hindol |
Sanjapada |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Sanjapada RD Road to UP School |
108 days |
Forward Pending |
| 24 |
Odisha |
Dhenkanal |
Hindol |
Madhapur |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Aounali Bandha |
108 days |
Forward Pending |
| 25 |
Odisha |
Dhenkanal |
Hindol |
Rasol |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at RD Road to Birikot Harizansahi Nuapatana |
108 days |
Forward Pending |
| 26 |
Odisha |
Dhenkanal |
Hindol |
Buhalipal |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Analabeda Kothaghar to Pradhansahi Analabeda |
108 days |
Forward Pending |
| 27 |
Odisha |
Dhenkanal |
Hindol |
Khaliborei |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Purunasahi to Kusuma Bandha |
108 days |
Forward Pending |
| 28 |
Odisha |
Dhenkanal |
Hindol |
Nabakishorepur |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Sabar Sahi |
108 days |
Forward Pending |
| 29 |
Odisha |
Dhenkanal |
Hindol |
Jarada |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Jarada Ambatela to Badajoda Nala |
108 days |
Forward Pending |
| 30 |
Odisha |
Dhenkanal |
Hindol |
Dandiri |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Ghodadian UPS to Ghodadia AWC |
108 days |
Forward Pending |
| 31 |
Odisha |
Dhenkanal |
Hindol |
Kalinga |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from PWD Road Matiasahi |
108 days |
Forward Pending |
| 32 |
Odisha |
Dhenkanal |
Hindol |
Gandanali |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Kharachuli UPS to Khalinala Kharachuli |
108 days |
Forward Pending |
| 33 |
Odisha |
Dhenkanal |
Hindol |
Gulehi |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Morei Bhuin to Koeiliana |
108 days |
Forward Pending |
| 34 |
Odisha |
Dhenkanal |
Hindol |
Nuabag |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road at Nuabag village Road to Canal |
108 days |
Forward Pending |
| 35 |
Odisha |
Dhenkanal |
Hindol |
Dudurukote |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from RD Road to Kaian Sahi |
108 days |
Forward Pending |
| 36 |
Odisha |
Kalahandi |
Kesinga |
Balsi |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from Balsi to Girigobardhan Mandir |
59 days |
Forward Pending |
| 37 |
Odisha |
Kalahandi |
Kesinga |
Balsi |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC Road at Rajpur, Rengali |
59 days |
Forward Pending |
| 38 |
Odisha |
Kalahandi |
Kesinga |
Belakhandi |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from PWD Road to Laxmipada at Talbhanra |
59 days |
Forward Pending |
| 39 |
Odisha |
Kalahandi |
Kesinga |
Boria |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road at Chicharla Kendupada Rasta |
59 days |
Forward Pending |
| 40 |
Odisha |
Kalahandi |
Kesinga |
Chancher |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from Sabarpada to Jujurang Road |
59 days |
Forward Pending |
| 41 |
Odisha |
Kalahandi |
Kesinga |
Chancher |
Sri Siddharth Sankar Swain |
Director PR |
Repair & Maintenance of Bhoipada Road at Amtha |
59 days |
Forward Pending |
| 42 |
Odisha |
Kalahandi |
Kesinga |
Deogaon |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from Deogaon Harijanpada to Tolbrahamni |
59 days |
Forward Pending |
| 43 |
Odisha |
Kalahandi |
Kesinga |
Kasrupada |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from Malipada to MIP Road at Ghantsola |
59 days |
Forward Pending |
| 44 |
Odisha |
Kalahandi |
Kesinga |
Kundabandh |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Sarkata Road at Gurjimunda |
59 days |
Forward Pending |
| 45 |
Odisha |
Kalahandi |
Kesinga |
Laitara |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from Karlabhadi to Dherenjore Road |
59 days |
Forward Pending |
| 46 |
Odisha |
Kalahandi |
Kesinga |
Nunmath |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from NH 26 to Kinerkela |
59 days |
Forward Pending |
| 47 |
Odisha |
Kalahandi |
Kesinga |
Paralasinga |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from Paralsinga Nuapada to Shiv Mandir Gabda Dangri |
59 days |
Forward Pending |
| 48 |
Odisha |
Kalahandi |
Kesinga |
Patharla |
Sri Siddharth Sankar Swain |
Director PR |
Construction of CC Road from PMGSY Road to VSS Building and Harijan Pada Goudtola |
59 days |
Forward Pending |
| 49 |
Odisha |
Kalahandi |
Kesinga |
Patharla |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from Patharla Basti to Bahadurpadar Road |
59 days |
Forward Pending |
| 50 |
Odisha |
Kalahandi |
Kesinga |
Sirol |
Sri Siddharth Sankar Swain |
Director PR |
Const. of Protection Wall at Deheranjore Road near Water Supply Tank, Sirol |
59 days |
Forward Pending |
| 51 |
Odisha |
Kalahandi |
Kesinga |
Utkela |
Sri Siddharth Sankar Swain |
Director PR |
Imp. of Road from Rigdimal to Sialjhudngi Road at Rigdimal |
59 days |
Forward Pending |
| 52 |
Odisha |
Gajapati |
Gumma |
Ajayagada |
Sri Siddharth Sankar Swain |
Director PR |
Construction of Culvert at Kanrumtin Sahi Bontilida |
65 days |
Forward Pending |
| 53 |
Odisha |
Gajapati |
Gumma |
Baijhal |
Sri Siddharth Sankar Swain |
Director PR |
Improvement road from Gomang Sahi to Minati Sahi at Udasing |
65 days |
Forward Pending |
| 54 |
Odisha |
Gajapati |
Gumma |
Brushava |
Sri Siddharth Sankar Swain |
Director PR |
Improvement road from Ababa to Kutta Sahi at Kutta |
65 days |
Forward Pending |
| 55 |
Odisha |
Gajapati |
Gumma |
Bhubani |
Sri Siddharth Sankar Swain |
Director PR |
Improvement road from Ababa to Tudumar Sahi at Tuburda |
65 days |
Forward Pending |
| 56 |
Odisha |
Gajapati |
Gumma |
Dumbada |
Sri Siddharth Sankar Swain |
Director PR |
Improvement road from Tabmegorjang Sahi to Barangsing Sahi at Tabmego |
65 days |
Forward Pending |
| 57 |
Odisha |
Gajapati |
Gumma |
Gaiba |
Sri Siddharth Sankar Swain |
Director PR |
Improvement road from Barubada road to Jakub Sahi at Oloiputa |
65 days |
Forward Pending |
| 58 |
Odisha |
Gajapati |
Gumma |
Munisingi |
Sri Siddharth Sankar Swain |
Director PR |
Improvement road from Church to Limasing Sahi |
65 days |
Forward Pending |
| 59 |
Odisha |
Gajapati |
Gumma |
Tarangada |
Sri Siddharth Sankar Swain |
Director PR |
Improvement road from Gamango Sahi to Church Sahi at Konda Parasambha |
65 days |
Forward Pending |
| 60 |
Odisha |
Gajapati |
Gumma |
Tumula |
Sri Siddharth Sankar Swain |
Director PR |
Repair and maintenance of road from Talaul to Ragidi Putta |
65 days |
Forward Pending |
| 61 |
Odisha |
Gajapati |
Gumma |
Ragidi |
Sri Siddharth Sankar Swain |
Director PR |
Repair and maintenance of road from Sarakun to Padursingi village |
65 days |
Forward Pending |
| 62 |
Odisha |
Puri |
Gop |
Andhra Ichhapur |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road at Dihuda nayak Sahi |
62 days |
Forward Pending |
| 63 |
Odisha |
Puri |
Gop |
Badatara |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Ogalpur Dash Sahi to Kesab, Harijan Sahi |
62 days |
Forward Pending |
| 64 |
Odisha |
Puri |
Gop |
Baniasahi |
Sri Siddharth Sankar Swain |
Director PR |
Const. CC road from PMGSY road to Segragation House |
62 days |
Forward Pending |
| 65 |
Odisha |
Puri |
Gop |
Bantaligram |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Mahapur Chaita Sethi house to Deba Mallick House |
62 days |
Forward Pending |
| 66 |
Odisha |
Puri |
Gop |
Bodapur |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Patelia Balikapileswar road to Das Sahi Biranchi Mohanty house |
62 days |
Forward Pending |
| 67 |
Odisha |
Puri |
Gop |
Davara |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Olandi Basudev Mandir to Mahaveer Temple road |
62 days |
Forward Pending |
| 68 |
Odisha |
Puri |
Gop |
Erabanga |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from RD road to Akhandalpur Brahamana Sahi |
62 days |
Forward Pending |
| 69 |
Odisha |
Puri |
Gop |
Ganeswarpur |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from RD Road, Ganeswarpur to Nilakanthanath temple |
62 days |
Forward Pending |
| 70 |
Odisha |
Puri |
Gop |
Gop |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Raju Das house to Bali Padia |
62 days |
Forward Pending |
| 71 |
Odisha |
Puri |
Gop |
Kuanpada |
Sri Siddharth Sankar Swain |
Director PR |
Imp. Of CC road from MB road to Kuanpada PMGSY. |
62 days |
Forward Pending |
| 72 |
Odisha |
Puri |
Gop |
Nagapur |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from ward No. 9 to Basanti Singh house |
62 days |
Forward Pending |
| 73 |
Odisha |
Puri |
Gop |
Nuakholamara |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road at Gabadiha Bhoi Sahi |
62 days |
Forward Pending |
| 74 |
Odisha |
Puri |
Gop |
Payara |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Gadasitha Harijan Sahi to Thakurani Temple |
62 days |
Forward Pending |
| 75 |
Odisha |
Puri |
Gop |
Rahangorada |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Rankoi Harijan Sahi to Balunkeswar |
62 days |
Forward Pending |
| 76 |
Odisha |
Puri |
Gop |
Chhaitana |
Sri Siddharth Sankar Swain |
Director PR |
Imp. Of road from Chhaitana Bazar to Dama Sahi |
62 days |
Forward Pending |
| 77 |
Odisha |
Puri |
Gop |
Gadabhingura |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Gadabhingura GP High School to Jamua |
62 days |
Forward Pending |
| 78 |
Odisha |
Puri |
Gop |
Itibhuan |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Chhaitana Bazar to Dhruba Nayak house at Kabirajpur |
62 days |
Forward Pending |
| 79 |
Odisha |
Puri |
Gop |
Boulanga |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Baulang Primary School to Baulanga Anganwadi Centre |
62 days |
Forward Pending |
| 80 |
Odisha |
Puri |
Gop |
Boulanga |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Barimunda Baliasahi to Majhisahi, Barimunda |
62 days |
Forward Pending |
| 81 |
Odisha |
Puri |
Gop |
Birtung |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Balichaka Road to Kalia Jena House, Girima |
62 days |
Forward Pending |
| 82 |
Odisha |
Puri |
Gop |
Birtung |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from NN Road to Mallick Sahi, Kanti |
62 days |
Forward Pending |
| 83 |
Odisha |
Puri |
Gop |
Birtung |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Sethi Sahi to Jageswari Thakurani, Gadakaramala |
62 days |
Forward Pending |
| 84 |
Odisha |
Puri |
Gop |
Birtung |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from PMGSY road to Samir Panda House, Girima |
62 days |
Forward Pending |
| 85 |
Odisha |
Puri |
Gop |
Desthali |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Sohana R.D road to Bipana Biswal House, Desthali |
62 days |
Forward Pending |
| 86 |
Odisha |
Puri |
Gop |
Desthali |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Sukanta Biswal House to Pindol Thakurani, Pindol |
62 days |
Forward Pending |
| 87 |
Odisha |
Puri |
Gop |
Mahalapada |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Orei Kothaghara to Orei Mahadev Temple |
62 days |
Forward Pending |
| 88 |
Odisha |
Puri |
Gop |
Simili |
Sri Siddharth Sankar Swain |
Director PR |
Const. & Repairing of CC road from Bansidhar Dalai House to Pradhan Sahi, Ansara |
62 days |
Forward Pending |
| 89 |
Odisha |
Puri |
Gop |
Sorava |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from R.D raod to PaikaSahi road via Sangram Keshari Nayak House, Sorava |
62 days |
Forward Pending |
| 90 |
Odisha |
Puri |
Gop |
Sorava |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Muruda Village Road to Routsahi Via Arun Rout House |
62 days |
Forward Pending |
| 91 |
Odisha |
Puri |
Gop |
Tarakor |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from PMGSY Road to Rasmiranjan Dalai House, Bangor |
62 days |
Forward Pending |
| 92 |
Odisha |
Puri |
Gop |
Tarakor |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road at Tarakor Danda Harijan Sahi, Tarakor |
62 days |
Forward Pending |
| 93 |
Odisha |
Gajapati |
Gumma |
Kujasingi |
Sri Siddharth Sankar Swain |
Director PR |
Repair & Manitanance of road from Kanheipur to Padhapana Street |
65 days |
Forward Pending |
| 94 |
Odisha |
Bhadrak |
Basudevpur |
Eram |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Mugeipada Chhaka to Gangadhar Ghadei House Vill-Sadeipada |
60 days |
Forward Pending |
| 95 |
Odisha |
Bhadrak |
Basudevpur |
Chudamani |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from PWD Road to Jata Mohakud House Vill-Chudamani |
60 days |
Forward Pending |
| 96 |
Odisha |
Bhadrak |
Basudevpur |
Biddeipur |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Karanjadia Road to Shridhar Bhoi House Ward No-8 Vill- Bideipur |
60 days |
Forward Pending |
| 97 |
Odisha |
Bhadrak |
Basudevpur |
Rajaharopokhari |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from near Bailochan Das House at Sana Machua Ghai |
60 days |
Forward Pending |
| 98 |
Odisha |
Bhadrak |
Basudevpur |
Bramhangan |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Bhagirathi Chaka to Panigrahi Sahi cahaka Vill- Manmathpur |
60 days |
Forward Pending |
| 99 |
Odisha |
Bhadrak |
Basudevpur |
Aruha |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Naichhanpur Canel to Narayan Jena Sahi Vill- Naichhanpur |
60 days |
Forward Pending |
| 100 |
Odisha |
Bhadrak |
Basudevpur |
Barandua |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Danagadi Pada to Swain sahi,Vill-Ratanga |
60 days |
Forward Pending |
| 101 |
Odisha |
Bhadrak |
Basudevpur |
Barandua |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from R&B Road to Nayak sahi via-Barik sahi,Vill-Barandua |
60 days |
Forward Pending |
| 102 |
Odisha |
Bhadrak |
Basudevpur |
Barandua |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Kuni Lenka House to Satura Mohanty Sahi Vill- Barandua |
60 days |
Forward Pending |
| 103 |
Odisha |
Bhadrak |
Basudevpur |
Barandua |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Mahendra Mohapatra House to Sridhar Sahu House Vill- Barandua |
60 days |
Forward Pending |
| 104 |
Odisha |
Puri |
Satyabadi |
Desabidyadharapur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Nimei badi road to Dhuna Bhoi house |
62 days |
Forward Pending |
| 105 |
Odisha |
Puri |
Satyabadi |
Sukal |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Pravakar Pradhan house to Mangala Temple of Gualipari |
62 days |
Forward Pending |
| 106 |
Odisha |
Puri |
Satyabadi |
Alisha |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Kachera Parida to khati maran |
62 days |
Forward Pending |
| 107 |
Odisha |
Puri |
Satyabadi |
Algum |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road at Bhoi sahi ward no 5 of Algum |
62 days |
Forward Pending |
| 108 |
Odisha |
Puri |
Satyabadi |
Narendrapur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Purna Chandra Behera house to Padmabati Temple at Paikasahi |
62 days |
Forward Pending |
| 109 |
Odisha |
Puri |
Satyabadi |
Sandharasasan |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Hiranyapada Upana Bhoi house to pokhari |
62 days |
Forward Pending |
| 110 |
Odisha |
Puri |
Satyabadi |
Biraramachandrpur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Srikanta Mishra hose to Chandi Temple patuari |
62 days |
Forward Pending |
| 111 |
Odisha |
Puri |
Satyabadi |
Madhubana |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Bramhan house to Prafula Sahoo house at Hatapada |
62 days |
Forward Pending |
| 112 |
Odisha |
Puri |
Satyabadi |
Nuasameswarpur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Bipina Swain house to Lokanatha Temple |
62 days |
Forward Pending |
| 113 |
Odisha |
Puri |
Satyabadi |
Kodua |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Bidyadhar Mallick house to Bhattapur village pond connecting RD road |
62 days |
Forward Pending |
| 114 |
Odisha |
Puri |
Satyabadi |
Penthapada |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Chintamani Book store to NH 316 |
62 days |
Forward Pending |
| 115 |
Odisha |
Puri |
Satyabadi |
Jayapur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Jayapur GP office to Mahamayasahi Sahi |
62 days |
Forward Pending |
| 116 |
Odisha |
Puri |
Satyabadi |
Biswanathpur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Laxmidhar Nayak house to Deba Bhoi house at Uttarsahi of Biswanathapur |
62 days |
Forward Pending |
| 117 |
Odisha |
Puri |
Satyabadi |
Dugal |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from River Embankment to Balunkeswar Temple |
62 days |
Forward Pending |
| 118 |
Odisha |
Puri |
Satyabadi |
Mulalasa |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Bauribandu Naik house to Swadhin Bharat Jena House |
62 days |
Forward Pending |
| 119 |
Odisha |
Puri |
Satyabadi |
Sri Ramachandrapur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Mathasahi School RD road to AWC Building |
62 days |
Forward Pending |
| 120 |
Odisha |
Puri |
Satyabadi |
Balapur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road at Bibhutibatika Bhogamandap |
62 days |
Forward Pending |
| 121 |
Odisha |
Puri |
Satyabadi |
Sarangjodi |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road at Palamandap Sarangajodi Bazar |
62 days |
Forward Pending |
| 122 |
Odisha |
Puri |
Satyabadi |
Raikhandi |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Tarini Temple to Dakhina khata at Suanlo |
62 days |
Forward Pending |
| 123 |
Odisha |
Puri |
Satyabadi |
Mahura |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Barik Sahi to Tuna sir House at Dubaipur |
62 days |
Forward Pending |
| 124 |
Odisha |
Puri |
Satyabadi |
Parajapada |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road at Mahaveer Mandap Kalapahad ward no 9 |
62 days |
Forward Pending |
| 125 |
Odisha |
Puri |
Satyabadi |
Bidyadharapur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road at Bidyadharpur Mohanty Sahi Ward no 4 |
62 days |
Forward Pending |
| 126 |
Odisha |
Puri |
Satyabadi |
Balarampur |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road at Balisahi Village School Road |
62 days |
Forward Pending |
| 127 |
Odisha |
Puri |
Satyabadi |
Ketakipatna |
Sri Siddharth Sankar Swain |
Director PR |
Const of CC road from Nilakantheswar Temple to Choudhury Sahi cremation ground |
62 days |
Forward Pending |
| 128 |
Odisha |
Kendrapara |
Pattamundai |
Oupada |
Sri Siddharth Sankar Swain |
Director PR |
CONSTRUCTION OF CC ROAD FROM MAIN ROAD TO SISHU MANDIR AT JUNUPANGA VILLAGE, GP- OUPADA |
62 days |
Forward Pending |
| 129 |
Odisha |
Bhadrak |
Basudevpur |
Artuna |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Nanchan Pokhari ghat to Ekdalia Bali Vill- Sankaru |
60 days |
Forward Pending |
| 130 |
Odisha |
Bhadrak |
Basudevpur |
Balimuinda |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Aditya Mandal house to Arun Mandal House Ward No- 11 Vill- Nandapatana |
60 days |
Forward Pending |
| 131 |
Odisha |
Bhadrak |
Basudevpur |
Binovabenagar |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Sanjay Barman House to Sanyasi Mandal House Vill-B.Bnagar |
60 days |
Forward Pending |
| 132 |
Odisha |
Bhadrak |
Basudevpur |
Gobindapur |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Kamalapada market Complex to Pani Tanki Gobindpur Vill- Gobindapur |
60 days |
Forward Pending |
| 133 |
Odisha |
Bhadrak |
Basudevpur |
Lunga |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Jaladhar Swain House to RD Road up to Hanuman Temple Vill- Kuruda |
60 days |
Forward Pending |
| 134 |
Odisha |
Bhadrak |
Basudevpur |
K.Binayakpur |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Sankarsan Panigrahi Sahi to Bagada Dash Sahi Bhagabata Tungi W. No-2 Vill- Bagada Binayakpur |
60 days |
Forward Pending |
| 135 |
Odisha |
Bhadrak |
Basudevpur |
Aruha |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Rath sahi to Aruha Vill- Aruha |
60 days |
Forward Pending |
| 136 |
Odisha |
Bhadrak |
Basudevpur |
Padmapur |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Mangaraj Behera Sahi to towards Sahada RD Road Vill- Kapagadia |
60 days |
Forward Pending |
| 137 |
Odisha |
Bhadrak |
Basudevpur |
Jagannathpur |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Chakradhar Kar House to RD Road Vill- Jaganathpur |
60 days |
Forward Pending |
| 138 |
Odisha |
Bhadrak |
Basudevpur |
Jagannathpur |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from PWD Road to via-Ramachandra Kar House Vill- Jaganathpur |
60 days |
Forward Pending |
| 139 |
Odisha |
Bhadrak |
Basudevpur |
Narasinghpur |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Parshu Das House to Gopal Das Sahi Ward No-02 Vill- Makhalpur |
60 days |
Forward Pending |
| 140 |
Odisha |
Bhadrak |
Basudevpur |
Barandua |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Muduli Sahi to Madhusudanpur Minor Vill- Madhusudanpur |
60 days |
Forward Pending |
| 141 |
Odisha |
Bhadrak |
Basudevpur |
Arandua |
Sri Siddharth Sankar Swain |
Director PR |
Improvement of road from Budha Pokhari chaka to Gopal Das Ghara Vill Chatria |
60 days |
Forward Pending |
| 142 |
Odisha |
Kalahandi |
Jayapatna |
Ranamal |
Sri Siddharth Sankar Swain |
Director PR |
Const. of CC road from Arebeda Badbandha to Basti road |
59 days |
Forward Pending |
| 143 |
Odisha |
Kalahandi |
Jayapatna |
Jaipatna |
Sri Siddharth Sankar Swain |
Director PR |
Const. of Paver block road from Tahsil office to Suresh Pattanaik house |
59 days |
Forward Pending |
| 144 |
Odisha |
Nabarangpur |
Raighar |
Bobei |
Sri Siddharth Sankar Swain |
Director PR |
Amo Sahi Rasta |
11 days |
Forward Pending |