| 1 |
Odisha |
Malkangiri |
Korukonda |
Kamwada |
Viplab Kumar Nayak |
Desk Officer |
Construction of RCC slab culvert from Kamwada Tala Sahi to MV-49 canal |
205 days |
| 2 |
Odisha |
Malkangiri |
Korukonda |
Dudametta |
Viplab Kumar Nayak |
Desk Officer |
Construction of RCC slab culvert from Koyaguda to Palmeta main canal |
205 days |
| 3 |
Odisha |
Sambalpur |
Dhankauda |
Kankhinda |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road from Bisipali village Road to Maharupada |
120 days |
| 4 |
Odisha |
Sambalpur |
Dhankauda |
Kilasama |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road from Padhanpali Harijanpada to Talipada |
120 days |
| 5 |
Odisha |
Sambalpur |
Dhankauda |
Kudgunderpur |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road from Dilip Pahdee House to Hanuman Mandir,Kud-Gunderpur |
120 days |
| 6 |
Odisha |
Sambalpur |
Dhankauda |
Sason |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road at Chhatargada |
120 days |
| 7 |
Odisha |
Sambalpur |
Dhankauda |
Kankhinda |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road at Munda Pipalpada Kankhinda |
120 days |
| 8 |
Odisha |
Khordha |
Balianta |
Kakaruidrapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD AT PANCHALO |
83 days |
| 9 |
Odisha |
Khordha |
Balianta |
Bentapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM BAISNAB SAHI TO MALLICK SAHI, W-1 |
83 days |
| 10 |
Odisha |
Khordha |
Balianta |
Jhinti Sasan |
Viplab Kumar Nayak |
Desk Officer |
MAINTENANCE OF CC ROAD FROM MAHIMAGADI TO BAPINA GOCHAYAT HOUSE |
83 days |
| 11 |
Odisha |
Khordha |
Balianta |
Prataprudrapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM BETANDA TO BALUNKESWARI PATAMAHADEV PITHA |
83 days |
| 12 |
Odisha |
Khordha |
Balianta |
Balianta |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM ATALA SMASAN ROAD, W-18 |
83 days |
| 13 |
Odisha |
Khordha |
Balianta |
Bhingarapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF DARA CHOUKA SMASAN ROAD, W-11 |
83 days |
| 14 |
Odisha |
Khordha |
Begunia |
Deuli |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Rohita muduli house to UP school via Dalak |
83 days |
| 15 |
Odisha |
Khordha |
Begunia |
Rasdhakantapur |
Viplab Kumar Nayak |
Desk Officer |
Construction ofCC Road from Dhangharnuagaon Khanibaghei temple to Banambar khatei house |
83 days |
| 16 |
Odisha |
Khordha |
Begunia |
Haja |
Viplab Kumar Nayak |
Desk Officer |
Construction of paikasahi CC Road |
83 days |
| 17 |
Odisha |
Khordha |
Begunia |
Siko |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from New Jagannath road to Belapada reading room |
83 days |
| 18 |
Odisha |
Khordha |
Begunia |
Govuindapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road near Ratna mandap vill-Bramhapura |
83 days |
| 19 |
Odisha |
Khordha |
Begunia |
Hirapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road in GP Office premises, Hirapur |
83 days |
| 20 |
Odisha |
Khordha |
Begunia |
Botalama |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road near Kapileswar temple premises, Badabarabati |
83 days |
| 21 |
Odisha |
Khordha |
Begunia |
Rautapada |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from new masjid to pradhan mantri sadak via Harijan sahi |
83 days |
| 22 |
Odisha |
Khordha |
Begunia |
Dingara |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Dahala devi kupa to Smasana CC Road |
83 days |
| 23 |
Odisha |
Khordha |
Begunia |
Baghamari |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from RI office to Raghunathdev High School back side |
83 days |
| 24 |
Odisha |
Khordha |
Begunia |
Badaberana |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Kalika Mandira to Akhadabara vill Gobindapur |
83 days |
| 25 |
Odisha |
Nuapada |
Boden |
Sunapur |
Viplab Kumar Nayak |
Desk Officer |
Repair & maintaince of Road at Sahajmal to Padampur |
68 days |
| 26 |
Odisha |
Nuapada |
Boden |
Rokal |
Viplab Kumar Nayak |
Desk Officer |
Construction of Culvert at Khirmal Debandha Road |
68 days |
| 27 |
Odisha |
Nuapada |
Boden |
Palsada |
Viplab Kumar Nayak |
Desk Officer |
Construction of Culvert at Palsada Juna Road |
68 days |
| 28 |
Odisha |
Nuapada |
Boden |
Damjhar |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road at Mandobirli Jayaram Gali |
68 days |
| 29 |
Odisha |
Nuapada |
Boden |
Boirgaon |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road at Khadupani Salepada Chandrabhanu Majhi Gaili |
68 days |
| 30 |
Odisha |
Khordha |
Balipatna |
Pampalo |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from Chanahata Aitalanga RD road on the Right side bank of Ankuspur canal to Sarat Jagir Telisahi near Krushna Sahoo House.w- |
83 days |
| 31 |
Odisha |
Khordha |
Balipatna |
Bhakarasahi |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Kushavadra Nadi Bandha to GBC canal Bridge at Naranpur of Ward No: 2 |
83 days |
| 32 |
Odisha |
Khordha |
Balipatna |
Guapur |
Viplab Kumar Nayak |
Desk Officer |
Repair & Maintenance of Guapur Dasarathi Mallick Hose to Kailash Mallick House, w- 04 |
83 days |
| 33 |
Odisha |
Khordha |
Balipatna |
Bhapur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Road from GBC Canal to Badadihapatna School |
83 days |
| 34 |
Odisha |
Khordha |
Chilika |
Badakula |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Rameswar Temple to NH-16. |
83 days |
| 35 |
Odisha |
Khordha |
Chilika |
Biribadi |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road near Jagannath Temple, Kaithapalla. |
83 days |
| 36 |
Odisha |
Khordha |
Chilika |
Haripur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Tuku Samantaray house to Sangram Sahoo House. |
83 days |
| 37 |
Odisha |
Khordha |
Chilika |
Sananasiri |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Sudhir Sahoo house to Trinath Palei farm at Badanairi. |
83 days |
| 38 |
Odisha |
Khordha |
Khordha |
Pallatotapada |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road nuapokhari huda |
83 days |
| 39 |
Odisha |
Khordha |
Khordha |
Orabarasingh |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road from Gula singh house to primary School |
83 days |
| 40 |
Odisha |
Khordha |
Khordha |
Golabaisasana |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road golabai society back side of ramesh pradhan house |
83 days |
| 41 |
Odisha |
Khordha |
Khordha |
Bajapur |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road from baniatangi UP ME School to Nilakantheswar Temple |
83 days |
| 42 |
Odisha |
Khordha |
Khordha |
Jankia |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road from Tapan barik house to Gudia Chua word No 11 |
83 days |
| 43 |
Odisha |
Khordha |
Khordha |
Brajamohanpur |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road form RD road to Behera Sahi |
83 days |
| 44 |
Odisha |
Khordha |
Khordha |
Kaipadara |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road form pala mandap to shiv temple |
83 days |
| 45 |
Odisha |
Khordha |
Khordha |
Kaipadara |
Viplab Kumar Nayak |
Desk Officer |
Improvement/repair & Maintenance of road from Dalei Sahi Champati Sahi Artikia dia to smashan |
83 days |
| 46 |
Odisha |
Nuapada |
Sinapali |
Kusumjore |
Viplab Kumar Nayak |
Desk Officer |
Repair & maintenance of Kasaipani Gahatiapada |
68 days |
| 47 |
Odisha |
Nuapada |
Sinapali |
Singjhar |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road of Gudimaa Gudi to Main Road at Pendren |
68 days |
| 48 |
Odisha |
Nuapada |
Sinapali |
Kharsel |
Viplab Kumar Nayak |
Desk Officer |
Const. of CC. Road at Kharsel Kolonipada at Kharsel |
68 days |
| 49 |
Odisha |
Nuapada |
Sinapali |
Ghatmal |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road at Gadhiajore Basti at Gadhiajore |
68 days |
| 50 |
Odisha |
Nuapada |
Sinapali |
Sinapali |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Sinapali college centeen road to Katapada road at Sardhapur |
68 days |
| 51 |
Odisha |
Nuapada |
Sinapali |
Nangalbod |
Viplab Kumar Nayak |
Desk Officer |
Impv. Of Road from Main Road to Tankamal basti |
68 days |
| 52 |
Odisha |
Nuapada |
Sinapali |
Sinapali |
Viplab Kumar Nayak |
Desk Officer |
Impv. Of Road from Samanta Dash house to Biju expressway at Kapsi |
68 days |
| 53 |
Odisha |
Nuapada |
Sinapali |
Kaintapadar |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road at Haldimunda Naik Pada to Bedi Chouk road |
68 days |
| 54 |
Odisha |
Khordha |
Bhubaneswar |
Basuaghai |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REAPAIR & MAINTENANCE OF ROAD FROM DEBAJOTI PATTNAIK HOUSE TO SOUTH SIDE, SUSHANTIBIHAR |
83 days |
| 55 |
Odisha |
Khordha |
Bhubaneswar |
Itipur |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF ROAD FROM PANCHAYAT ROAD TO KESHAB SWAIN HOUSE AT NISTARINIPUR |
83 days |
| 56 |
Odisha |
Khordha |
Bhubaneswar |
Itipur |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF ROAD FROM CANAL BANDHA TO KARTIK SWAIN HOUSE, KUKUDAGHAIPATNA |
83 days |
| 57 |
Odisha |
Khordha |
Bhubaneswar |
Ranasinghpur |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF ROAD FROM BHUBAN APARTMENT CHHAKA TO HANUMAN TEMPLE |
83 days |
| 58 |
Odisha |
Khordha |
Bhubaneswar |
Sisupalagarh |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF PANDA SAHI ROAD |
83 days |
| 59 |
Odisha |
Khordha |
Bhubaneswar |
Malipada |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF ROAD FROM GOTHAPATNA MAIN ROAD TO MANTRA APARTMENT |
83 days |
| 60 |
Odisha |
Khordha |
Bhubaneswar |
Daruthenga |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF XAVIER SCHOOL TO GADASAHI ROAD |
83 days |
| 61 |
Odisha |
Khordha |
Bhubaneswar |
Tikarapada |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF ROAD FROM PRAKASH HOUSE TO THAKURANI TEMPLE NUASAHI AT KALYANPURSASAN |
83 days |
| 62 |
Odisha |
Khordha |
Bhubaneswar |
Itipur |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF ROAD FROM BASU BARAL HOUSE TO ASHRAM AT DIHAPUR |
83 days |
| 63 |
Odisha |
Khordha |
Bhubaneswar |
Sisupalagarh |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT/REPAIR & MAINTENANCE OF MANGALA BHOISAHI CC ROAD |
83 days |
| 64 |
Odisha |
Balasore |
Baliapal |
Madhupura |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road and bridge from Majhisahi Bhagabat Tungi to Solasa Pantha. |
120 days |
| 65 |
Odisha |
Balasore |
Baliapal |
Srirampur |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Adibasi Sahi Chhera Soren house chhak to Mainsamunda Shmasan Chhak at Mainsamunda. |
120 days |
| 66 |
Odisha |
Balasore |
Baliapal |
Balikuti |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Raghunath Rout house to Amulya Biswal house at Baitingiri |
120 days |
| 67 |
Odisha |
Balasore |
Baliapal |
Dagara |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Prafulla Patra house to Sea-Shore. |
120 days |
| 68 |
Odisha |
Balasore |
Baliapal |
Bishnupur |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Ikarpal Siva mandir to Ikarpal Substation Chhak |
120 days |
| 69 |
Odisha |
Balasore |
Baliapal |
Jagatipur |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from PWD road to Kalicharan Parmanik house at village Ranikhudi |
120 days |
| 70 |
Odisha |
Balasore |
Baliapal |
Kunduli |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Sunadiha Chhak to Sunadiha bridge at village Indipada |
120 days |
| 71 |
Odisha |
Balasore |
Baliapal |
Nuagan |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Katara Mahal tungi chhak to Ramchandra Giri chhak at village Katara Mahal |
120 days |
| 72 |
Odisha |
Balasore |
Baliapal |
Aladiha |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Sai Jiban Mohanty house to Khagendra Biswal house at village Anladiha |
120 days |
| 73 |
Odisha |
Balasore |
Baliapal |
Bahiapal |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Bright Computer Institution to Bansidhar Jena house at village Kachuapada |
120 days |
| 74 |
Odisha |
Balasore |
Baliapal |
Pratappur |
Viplab Kumar Nayak |
Desk Officer |
Repair and maintenance of Road from Purushottam Barik house to Niasi Charan Rout house at village Pratappur ward no-9 |
120 days |
| 75 |
Odisha |
Khordha |
Jatni |
Benapanjari |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM SAHA AJIN ALI HOUSE TO MD NABIN HOUSE, BENAPANJARI |
83 days |
| 76 |
Odisha |
Khordha |
Jatni |
Benapanjari |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM BHASKARA CHAMPATI HOUSE TO RAJIDI PATTANAIK HOUSE , BENAPANJARI |
83 days |
| 77 |
Odisha |
Khordha |
Jatni |
Gangapada |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM SINGHA SAHI BHAGABAT HOUSE TO KELU PRADHAN HOUSE, GANGAPADA |
83 days |
| 78 |
Odisha |
Khordha |
Jatni |
Angarapada |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM MAHAVIR TEMPLE TO GOURANGA SAHOO HOUSE , PALASPUR, ANGARAPADA |
83 days |
| 79 |
Odisha |
Khordha |
Jatni |
Chhatabara |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM GANGA SAHOO HOUSE TO BIBI NAYAK HOUSE , DURGAPUR , CHHATABAR |
83 days |
| 80 |
Odisha |
Khordha |
Jatni |
Taraboi |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM HARIDAMADA SCHOOL TO MAKRAMALI HOUSE , HARIDAMADA, TARABOI |
83 days |
| 81 |
Odisha |
Nuapada |
Khariar |
Tukla |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Road from Rengtapada to Sannandi Bridge |
68 days |
| 82 |
Odisha |
Nuapada |
Khariar |
Sanmaheswar |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Road from Sanmaheswar Colonypada via Shyama Sabar House |
68 days |
| 83 |
Odisha |
Nuapada |
Khariar |
Nehena |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road at Nehena Khamaripada |
68 days |
| 84 |
Odisha |
Nuapada |
Khariar |
Lanji |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Mainroad to Dambaru Harijan Pada Gali |
68 days |
| 85 |
Odisha |
Nuapada |
Khariar |
Kendupati |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road at Banchhorpada (Khaliamunda) |
68 days |
| 86 |
Odisha |
Khordha |
Bolagarh |
Khanguria |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF RD ROAD TO MUKTAR KHAN HOUSE ROAD |
83 days |
| 87 |
Odisha |
Khordha |
Bolagarh |
Khanguria |
Viplab Kumar Nayak |
Desk Officer |
HARIPUR TO HARIPUR SMASAN ROAD |
83 days |
| 88 |
Odisha |
Khordha |
Bolagarh |
Gediapalli |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF P.W.D. ROAD TO BRAMHANI DEVI TEMPLE ROAD, SALATARA |
83 days |
| 89 |
Odisha |
Khordha |
Bolagarh |
Mnibandha |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CULVET AT MANIBANDHA TO BADAPADAR NALA |
83 days |
| 90 |
Odisha |
Khordha |
Bolagarh |
Daleisahi |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD FROM DEBRAJ FARM TO ( WARD NO-18 ) SONA NAI AT DALEISAHI GP |
83 days |
| 91 |
Odisha |
Khordha |
Bolagarh |
Khanguria |
Viplab Kumar Nayak |
Desk Officer |
RAMA MANDIR CAMPUS CC ROAD (JODAPADA) |
83 days |
| 92 |
Odisha |
Khordha |
Bolagarh |
Fasioda |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF KELA PARIDA HOUSE TO MANGALA TEMPLE ROAD, MANDALSINGH |
83 days |
| 93 |
Odisha |
Nuapada |
Komna |
Darlipada |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF GUARD WALL WITH CULVERT AT DUMERPANI AWC TO GADIPUJAGUDI OF DARLIPADA GP |
68 days |
| 94 |
Odisha |
Nuapada |
Komna |
Silva |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF 2 NOS OF CULVERT FROM CHHUTIGUDI TO MURGAFIELD ROAD SILVA GP |
68 days |
| 95 |
Odisha |
Nuapada |
Komna |
Thagapali |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CULVERT FROM BABUPALI BASTI TOWARDS VSS BUILDING |
68 days |
| 96 |
Odisha |
Nuapada |
Komna |
Mundapala |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CULVERT FROM SUABAHAL TO KHETRA MOHANPADA OF MUNDAPALA GP |
68 days |
| 97 |
Odisha |
Nuapada |
Komna |
Jadamunda |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF TITLIMUNDA CULVERT AT THONGO OF JADAMUNDA GP |
68 days |
| 98 |
Odisha |
Nuapada |
Nuapada |
Godfula |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Chatanpada to Patparpali village |
68 days |
| 99 |
Odisha |
Nuapada |
Nuapada |
Beltukri |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Barakothi to Mararpada to Tariapada |
68 days |
| 100 |
Odisha |
Nuapada |
Nuapada |
Parkod |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from PWD road to Semeria Dharsa road |
68 days |
| 101 |
Odisha |
Nuapada |
Nuapada |
Chulabhat |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Supli basti to Keutpada |
68 days |
| 102 |
Odisha |
Khordha |
Banapur |
Ayatpur |
Viplab Kumar Nayak |
Desk Officer |
Repair and Maintance of Bridge at TotaGaon |
83 days |
| 103 |
Odisha |
Khordha |
Banapur |
Nachuni |
Viplab Kumar Nayak |
Desk Officer |
implimentation of Nachuni college road |
83 days |
| 104 |
Odisha |
Khordha |
Banapur |
Bhabanipur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road Gateswarpur Sanapokhari north side road |
83 days |
| 105 |
Odisha |
Khordha |
Banapur |
Damiabarabara |
Viplab Kumar Nayak |
Desk Officer |
Construction of culvert and Guardwall at Gurupada Nuagaon |
83 days |
| 106 |
Odisha |
Khordha |
Tangi |
Sanarautapada |
Viplab Kumar Nayak |
Desk Officer |
Protection wall with CC road at Sanaroutapada Smasan Road |
83 days |
| 107 |
Odisha |
Khordha |
Tangi |
Mangalajodi |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from Kalyan Mandap to Baghei Thakurani |
83 days |
| 108 |
Odisha |
Khordha |
Tangi |
Dia |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from Dia Canal Bandha to Jagannath Sadak |
83 days |
| 109 |
Odisha |
Khordha |
Tangi |
Khunjjuri |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from NH-16 to Subarnapur |
83 days |
| 110 |
Odisha |
Khordha |
Tangi |
Nirakarpur |
Viplab Kumar Nayak |
Desk Officer |
Imp. Of CC road at Ratha Colony, Nirakarpur |
83 days |
| 111 |
Odisha |
Khordha |
Tangi |
Sundarapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from Ramalila Padia to Durgapuja Padia at Sundarpur Badasahi |
83 days |
| 112 |
Odisha |
Khordha |
Tangi |
Balipatapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from Badrinath Maharana House to Bada Pokhari at Deulasahi |
83 days |
| 113 |
Odisha |
Khordha |
Tangi |
Badapari |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from RD road to Raja Sundara House at Badapari |
83 days |
| 114 |
Odisha |
Khordha |
Tangi |
Ramachandrapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from Amina Bhola House to Dahaldei Temple at Singarama |
83 days |
| 115 |
Odisha |
Puri |
Kakat Pur |
Suhagpur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road with Culvert from Khola Pokhari to Maharana House |
83 days |
| 116 |
Odisha |
Puri |
Kakat Pur |
Kaduanuagaon |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Kumar Khantia to Gopal sahi smasan |
83 days |
| 117 |
Odisha |
Puri |
Kakat Pur |
Kakatpur |
Viplab Kumar Nayak |
Desk Officer |
Repairing of road from Mangala College Gate to Prachi river Bridge |
83 days |
| 118 |
Odisha |
Puri |
Kakat Pur |
Kantapada |
Viplab Kumar Nayak |
Desk Officer |
Repairing of Nilakanthapur Bhoi sahi Road |
83 days |
| 119 |
Odisha |
Puri |
Kakat Pur |
Abadan |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Nadiamatha RD road to Banambar Mahadev Temple road |
83 days |
| 120 |
Odisha |
Khordha |
Chilika |
Dungamal (Ct) |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM JHUNU BEHERA HOUSE TO RAJKISHORE PRADHAN HOUSE |
83 days |
| 121 |
Odisha |
Khordha |
Chilika |
Chndeswar |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT OF ROAD NEAR PUTANA AMRIT SAROVAR |
83 days |
| 122 |
Odisha |
Puri |
Nimapada |
Badasirivila |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road of Bhagabansundara Canal road |
83 days |
| 123 |
Odisha |
Puri |
Nimapada |
Balanga |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road in front of Balanga Police Station old water tank to P.S end |
83 days |
| 124 |
Odisha |
Puri |
Nimapada |
Bhiligram |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road at Jhampulakuda Satsang Colony |
83 days |
| 125 |
Odisha |
Puri |
Nimapada |
Bhiligram |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road Maniadiha village road |
83 days |
| 126 |
Odisha |
Puri |
Nimapada |
Chanrapada |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road from Bhatabandha road to Koli Pokhari road |
83 days |
| 127 |
Odisha |
Puri |
Nimapada |
Chhanijanga |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road & Culvert from Bhogasalada main road to water tank |
83 days |
| 128 |
Odisha |
Puri |
Nimapada |
Deuna |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road from Raghunath Nayak house to Narendra Biswal House , Ratnakar Bihar |
83 days |
| 129 |
Odisha |
Puri |
Nimapada |
Dhanua |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road & Culvert at Safei at Baulapada village |
83 days |
| 130 |
Odisha |
Puri |
Nimapada |
Miteipur |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road from Jatadhari Jena house to Rabindra Swain house, Kaduapatna |
83 days |
| 131 |
Odisha |
Puri |
Nimapada |
Sainsasasan |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road Kasipur Brahman sahi road |
83 days |
| 132 |
Odisha |
Puri |
Nimapada |
Tampalo |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road Panchabatia village road |
83 days |
| 133 |
Odisha |
Puri |
Nimapada |
Tampalo |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Road from Panchabatia village road to Panchayat Pokhari |
83 days |
| 134 |
Odisha |
Nayagarh |
Nuagaon |
Sorada |
Viplab Kumar Nayak |
Desk Officer |
Const. of cc road at Jagannathprasad HS back side |
83 days |
| 135 |
Odisha |
Nayagarh |
Nuagaon |
Sikrida |
Viplab Kumar Nayak |
Desk Officer |
Const. of cc road from Sikrida to Jagannathprasad |
83 days |
| 136 |
Odisha |
Nayagarh |
Nuagaon |
Nuagaon |
Viplab Kumar Nayak |
Desk Officer |
Const. of cc road at Block Colony/Premises |
83 days |
| 137 |
Odisha |
Nayagarh |
Nuagaon |
Paradhipi |
Viplab Kumar Nayak |
Desk Officer |
Const. of cc road from Abhayapur Nuasahi to Balanda |
83 days |
| 138 |
Odisha |
Nayagarh |
Nuagaon |
Dhenkena |
Viplab Kumar Nayak |
Desk Officer |
Improvement of CC Road and Culvert from Madhuban to Malabandha |
83 days |
| 139 |
Odisha |
Khordha |
Balipatna |
Athantara |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road from Diba Bhoi house to Maa Khetrapal Temple, Barilo |
83 days |
| 140 |
Odisha |
Khordha |
Balipatna |
Athantara |
Viplab Kumar Nayak |
Desk Officer |
Repair & maintenance of Road from Maa mangala Temple to Binay Nayak House |
83 days |
| 141 |
Odisha |
Khordha |
Balipatna |
Alisisasan |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road pakuna nanda shop to Amiya sahoo house |
83 days |
| 142 |
Odisha |
Khordha |
Balipatna |
Alisisasan |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of road from Bhairpur melana padia masani to baliachatura culvert |
83 days |
| 143 |
Odisha |
Khordha |
Balipatna |
Rajasa |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road inside Rajas PHC Premises |
83 days |
| 144 |
Odisha |
Kendrapara |
Kendrapada |
Kapaleswar |
Viplab Kumar Nayak |
Desk Officer |
Repair & Maintenance of road from VIP road to Garapur RI Office |
120 days |
| 145 |
Odisha |
Nayagarh |
Gania |
Kishoreprasad |
Viplab Kumar Nayak |
Desk Officer |
CC road from bus stop to Brahmana sahi road |
83 days |
| 146 |
Odisha |
Nayagarh |
Gania |
Chhamundia |
Viplab Kumar Nayak |
Desk Officer |
CC road at malisahi |
83 days |
| 147 |
Odisha |
Nayagarh |
Gania |
Adakata |
Viplab Kumar Nayak |
Desk Officer |
CC road kenduabida to tamarajhola |
83 days |
| 148 |
Odisha |
Nayagarh |
Gania |
Karadapada |
Viplab Kumar Nayak |
Desk Officer |
Arjunkholo cc road nuapada |
83 days |
| 149 |
Odisha |
Nayagarh |
Gania |
Belapadapatna |
Viplab Kumar Nayak |
Desk Officer |
CC road mali sahi taladanada school to malatiput |
83 days |
| 150 |
Odisha |
Nayagarh |
Gania |
Rasanga |
Viplab Kumar Nayak |
Desk Officer |
rasang harijan sahi to high school culvert with cc |
83 days |
| 151 |
Odisha |
Nayagarh |
Gania |
Gania |
Viplab Kumar Nayak |
Desk Officer |
Gania paikasahi to pokhari road cc at gania |
83 days |
| 152 |
Odisha |
Nayagarh |
Odagaon |
Angisingi |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Angisingi Bridge to Puania road |
83 days |
| 153 |
Odisha |
Nayagarh |
Odagaon |
Dimisira |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Dimisar village road |
83 days |
| 154 |
Odisha |
Nayagarh |
Odagaon |
Pantikhari |
Viplab Kumar Nayak |
Desk Officer |
Const. of CC road at Pantikhari Belapada Sahi |
83 days |
| 155 |
Odisha |
Nayagarh |
Odagaon |
Bhadikila |
Viplab Kumar Nayak |
Desk Officer |
Const. of Ragadimada Golasahi CC road |
83 days |
| 156 |
Odisha |
Nayagarh |
Odagaon |
Badagodada |
Viplab Kumar Nayak |
Desk Officer |
Const. of CC road from Jagnnath Sadak to Barisahi road,vill-sanagorada |
83 days |
| 157 |
Odisha |
Nayagarh |
Odagaon |
Banthapur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Nepal village road |
83 days |
| 158 |
Odisha |
Nayagarh |
Odagaon |
Kurala |
Viplab Kumar Nayak |
Desk Officer |
Nauriagada smasan CC road |
83 days |
| 159 |
Odisha |
Cuttack |
Salepur |
Balisahi |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM UPA BARIK HOUSE TO CHITTA MOHANTY HOUSE, RODHAPUR, BALISAHI |
83 days |
| 160 |
Odisha |
Cuttack |
Salepur |
Bhimdaspur |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF TALAPADA BARAL SAHI ROAD |
83 days |
| 161 |
Odisha |
Cuttack |
Salepur |
Champati |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM JITENDRA BHUYAN HOUSE TO KENDRAPADA CANAL, WARD NO. 10, SATABATIA |
83 days |
| 162 |
Odisha |
Cuttack |
Salepur |
Mahana |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM MUSLIM SAHI TO CHAKA ROAD, MAHAN |
83 days |
| 163 |
Odisha |
Cuttack |
Salepur |
Raisunguda |
Viplab Kumar Nayak |
Desk Officer |
MAINTENANCE AND IMPROVEMENT OF ROAD FROM KUSAMBI MUSLIM SAHI TO ROUT SAHI, WARD NO. 16, KUSAMBI |
83 days |
| 164 |
Odisha |
Cuttack |
Salepur |
Paschimakachha |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM KOCHILEI TEMPLE TO BANIA SAHI, WARD NO. 10 |
83 days |
| 165 |
Odisha |
Cuttack |
Salepur |
Purunahat |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF BELERA VILLAGE ROAD |
83 days |
| 166 |
Odisha |
Cuttack |
Salepur |
Raisunguda |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM MURALI NAYAK HOUSE TO AKSHYA MOHAPATRA HOUSE, VILLAGE-MADHANGA |
83 days |
| 167 |
Odisha |
Cuttack |
Salepur |
Sidho |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM KHAIRA BISWAL SAHI TO 4F CANAL ROAD, KHAIRA |
83 days |
| 168 |
Odisha |
Cuttack |
Salepur |
Trilochanpur |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM GORA CHACHA HOUSE TO GULJAR KHAN HOUSE, KOTHABADA |
83 days |
| 169 |
Odisha |
Cuttack |
Salepur |
Satyabhamapur |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENACE OF CC ROAD FROM BULA PANI HOUSE TO GANESWAR MUKTESWAR TEMPLE , GANESWARPUR |
83 days |
| 170 |
Odisha |
Cuttack |
Salepur |
Gopinathpur |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF CC ROAD FROM BHARATI BHUSAN DAS HOUSE TO MAIN ROAD, GOPINATHAPUR |
83 days |
| 171 |
Odisha |
Cuttack |
Salepur |
Madhyakachha |
Viplab Kumar Nayak |
Desk Officer |
REPAIR & MAINTENANCE OF ROAD FROM CANNAL BANDHA TO AKHANDALAMANI MANDIRA, BARAGODIA, WARD NO-12 |
83 days |
| 172 |
Odisha |
Cuttack |
Salepur |
Purunahat |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENACE OF ROAD FROM GANGAPUR THAKURANI TO SATYABADI CHAINI HOUSE, GANGAPUR |
83 days |
| 173 |
Odisha |
Cuttack |
Salepur |
Mutarifa |
Viplab Kumar Nayak |
Desk Officer |
REPAIR & MAINTENANCE OF ROAD FROM WARD NO-1 CHAKKA TO PRAFULLA SAHU HOUSE, MUTARIFA |
83 days |
| 174 |
Odisha |
Cuttack |
Salepur |
Ratilo |
Viplab Kumar Nayak |
Desk Officer |
REPAIR & MAINTENANCE OF CC ROAD FROM KURULI BADA POLA TO MOHANTY SAHI, KURULI |
83 days |
| 175 |
Odisha |
Cuttack |
Salepur |
Trilochanpur |
Viplab Kumar Nayak |
Desk Officer |
REPAIR & MAINTENANCE OF ROAD FROM BHASKARA SAHOO HOUSE TO KALA BHAIRABI LAND, TRILOCHANAPUR WARD NO-8 |
83 days |
| 176 |
Odisha |
Cuttack |
Salepur |
Sidho |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF CC ROAD FROM 5 NO CANNAL TO RAMA NAYAK HOUSE, SIDHO |
83 days |
| 177 |
Odisha |
Cuttack |
Salepur |
Rameswar |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF CC ROAD FROM HANUMAN MANDIR TO AKULI PRADHAN HOUSE. SANYASIPATANA |
83 days |
| 178 |
Odisha |
Nuapada |
Komna |
Maniguda |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT OF ROAD FROM NAIKPADA TO GANIARY |
68 days |
| 179 |
Odisha |
Nuapada |
Komna |
Poinr |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT OF ROAD FROM POINR GP OFFICE TOWARDS MAHULBHATA OF POINR GP |
68 days |
| 180 |
Odisha |
Khordha |
Chilika |
Biribadi |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT OF ROAD NEAR RURAL PARK KAITHAPALLA,BIRIBADI |
83 days |
| 181 |
Odisha |
Khordha |
Chilika |
Haripur |
Viplab Kumar Nayak |
Desk Officer |
IMPROVEMENT OF ROAD AT RURAL PARK HARIPUR |
83 days |
| 182 |
Odisha |
Khordha |
Banapur |
Galua |
Viplab Kumar Nayak |
Desk Officer |
IMP OF ROAD FROM KAPILABIDYAPITHA AT BHIMPUR |
83 days |
| 183 |
Odisha |
Khordha |
Banapur |
Bhabanipur |
Viplab Kumar Nayak |
Desk Officer |
IMP OF ROAD GATESWARPUR SANAPOKHARI NORTH SIDE ROAD |
83 days |
| 184 |
Odisha |
Khordha |
Bolagarh |
Khanguria |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF RD ROAD TO MUKTAR KHAN HOUSE ROAD |
83 days |
| 185 |
Odisha |
Khordha |
Bolagarh |
Khanguria |
Viplab Kumar Nayak |
Desk Officer |
HARIPUR TO HARIPUR SMASAN ROAD |
83 days |
| 186 |
Odisha |
Khordha |
Bhubaneswar |
Basuaghai |
Viplab Kumar Nayak |
Desk Officer |
Improvement/Repair & Maintenance of road from Debajoti Pattnaik house to South Side,Sushantibihar |
83 days |
| 187 |
Odisha |
Khordha |
Bhubaneswar |
Itipur |
Viplab Kumar Nayak |
Desk Officer |
Improvement/Repair & Maintenance of road from Panchayat Road to Keshab Swain House at Nistarinipur |
83 days |
| 188 |
Odisha |
Khordha |
Bhubaneswar |
Ranasinghpur |
Viplab Kumar Nayak |
Desk Officer |
Improvement/Repair & Maintenance of road from Bhuban Apartment Chhaka to Hanuman Temple |
83 days |
| 189 |
Odisha |
Khordha |
Bhubaneswar |
Malipada |
Viplab Kumar Nayak |
Desk Officer |
Improvement/Repair & Maintenance of road from Gothapatna Main road to Mantra Apartment |
83 days |
| 190 |
Odisha |
Khordha |
Balianta |
Kakaruidrapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD AT PANCHALO ROAD |
83 days |
| 191 |
Odisha |
Khordha |
Tangi |
Sanarautapada |
Viplab Kumar Nayak |
Desk Officer |
PROTECTION WALL WITH CC ROAD AT SANAROUTAPADA SMASAN ROAD |
83 days |
| 192 |
Odisha |
Khordha |
Tangi |
Mangalajodi |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM KALYAN MANDAP TO BAGHEI THAKURANI MANGALAJODI |
83 days |
| 193 |
Odisha |
Khordha |
Tangi |
Dia |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM DIA CANAL BANDHA TO JAGANNATH SADAK |
83 days |
| 194 |
Odisha |
Khordha |
Tangi |
Khunjjuri |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM NH16 TO SUBARNAPUR KUNJURI |
83 days |
| 195 |
Odisha |
Khordha |
Balianta |
Bentapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM BAISNAB SAHI TO MALLICK SAHI, W-01 |
83 days |
| 196 |
Odisha |
Khordha |
Balianta |
Jhinti Sasan |
Viplab Kumar Nayak |
Desk Officer |
MAINTENANCE OF CC ROAD FROM MAHIMA GADI TO BAPINA GOCHAYAT HOUSE |
83 days |
| 197 |
Odisha |
Khordha |
Balianta |
Prataprudrapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF CC ROAD FROM BETENDA TO BALUNKESWARI PATAMAHADEV PITHA |
83 days |
| 198 |
Odisha |
Khordha |
Balianta |
Bhingarapur |
Viplab Kumar Nayak |
Desk Officer |
CONSTRUCTION OF DARA CHOUKA SMASAN ROAD , W-11 |
83 days |
| 199 |
Odisha |
Khordha |
Jatni |
Angarapada |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM MAHAVIR TEMPLE TO GAURANGA SAHOO HOUSE ,PALASPUR, ANGARAPADA. |
83 days |
| 200 |
Odisha |
Khordha |
Jatni |
Taraboi |
Viplab Kumar Nayak |
Desk Officer |
REPAIR AND MAINTENANCE OF ROAD FROM HARIDAMADA SCHOOL TO MAKRAMALI HOUSE, HARIDAMADA, TARABOI |
83 days |
| 201 |
Odisha |
Khordha |
Begunia |
Deuli |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD FROM ROHITA MUDULI HOUSE TO UP SCHOOL VIA DALAK |
83 days |
| 202 |
Odisha |
Khordha |
Begunia |
Botalama |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD NEAR KAPILESWAR TEMPLE PREMISES, BADABARABATI |
83 days |
| 203 |
Odisha |
Khordha |
Begunia |
Govuindapur |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD NEAR RATNA MANDAP, BRAHMAPURA |
83 days |
| 204 |
Odisha |
Khordha |
Begunia |
Begunia |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD FROM BHAGABAT GHAR TO ABAKASH MOHAPATRA HOUSE AT BHOIPUR |
83 days |
| 205 |
Odisha |
Khordha |
Balipatna |
Athantara |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC Road from Diba Bhoi House to Maa Khetrapal Temple, Barilo |
83 days |
| 206 |
Odisha |
Khordha |
Balipatna |
Rajasa |
Viplab Kumar Nayak |
Desk Officer |
Maintenance CC Road inside Rajas PHC Premises |
83 days |
| 207 |
Odisha |
Khordha |
Balipatna |
Alisisasan |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road Pakuna Nanda Shop to Aniya Sahoo house |
83 days |
| 208 |
Odisha |
Gajapati |
Rayagad |
Jalango |
Viplab Kumar Nayak |
Desk Officer |
Completion of incomplete Culvert bridge at Dumba village of Jallango |
68 days |
| 209 |
Odisha |
Gajapati |
Rayagad |
Karadasingi |
Viplab Kumar Nayak |
Desk Officer |
Completion of Incomplete CD Work at S.Kalamasing |
68 days |
| 210 |
Odisha |
Gajapati |
Rayagad |
Kumulsing |
Viplab Kumar Nayak |
Desk Officer |
Construction of CD Work at Tinkoda village of Kumulasing |
68 days |
| 211 |
Odisha |
Gajapati |
Rayagad |
Karadasingi |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Road at Harijana Sahi Burujanga Village |
68 days |
| 212 |
Odisha |
Gajapati |
Rayagad |
Sanatundi |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Road at GP Office to School Ghara Sanatundi |
68 days |
| 213 |
Odisha |
Khordha |
Khordha |
Kaipadara |
Viplab Kumar Nayak |
Desk Officer |
Improvement and Repair of road from Pala mandap to Shiv temple & Maintenace |
83 days |
| 214 |
Odisha |
Khordha |
Khordha |
Kaipadara |
Viplab Kumar Nayak |
Desk Officer |
Improvement and Repair & Maintenace of road from Dalei sahi Champati Sahi Artikia dia to Smasana |
83 days |
| 215 |
Odisha |
Khordha |
Khordha |
Khuradhamalla |
Viplab Kumar Nayak |
Desk Officer |
Const.of CC road from Sialia Adivasi sahi to Xavier School |
83 days |
| 216 |
Odisha |
Nayagarh |
Gania |
Chhamundia |
Viplab Kumar Nayak |
Desk Officer |
MUDULIGADIA BEHERA SAHI CC |
83 days |
| 217 |
Odisha |
Puri |
Pipili |
Kanti |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD AT NIJIGADAKURUKHI PATRA SAHI CHIKU BISWAL HOSE TO DHALA SAHI ROAD |
68 days |
| 218 |
Odisha |
Puri |
Pipili |
Orkal |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD AT GOBARDHANAPUR SULTAN NAGAR KANAS MINOR CANAL TO PURNA SWAIN POULTRY FARM |
68 days |
| 219 |
Odisha |
Puri |
Pipili |
Rulpadeipur |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF BAULACHAUKA BEHERA SAHI CC ROAD |
68 days |
| 220 |
Odisha |
Puri |
Pipili |
Chandradeipur |
Viplab Kumar Nayak |
Desk Officer |
REPAIR & MAINTANCE OF KAMAKANTIA VILL. CC ROAD WITH PAVER WORKS |
68 days |
| 221 |
Odisha |
Puri |
Pipili |
Kulasekharapatana |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF DRAIN AT ABALPUR DAS SAHI |
68 days |
| 222 |
Odisha |
Puri |
Pipili |
Pamasara |
Viplab Kumar Nayak |
Desk Officer |
REPAIR & MAINTANCE OF KAIRI VILL. CC ROAD AT WARD NO 8 & 9 (VILLAGE MAIN ROAD) |
68 days |
| 223 |
Odisha |
Puri |
Pipili |
Jasuapur |
Viplab Kumar Nayak |
Desk Officer |
CONST. OF CC ROAD FROM LAXMAN PRADHAN HOUSE TO ROAD END WORD NO -4 |
68 days |
| 224 |
Odisha |
Gajapati |
Nuagada |
Sundardanga |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Paikapada to Anupur |
68 days |
| 225 |
Odisha |
Gajapati |
Nuagada |
Udayapur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from RD road to AWC centre,Udayapur |
68 days |
| 226 |
Odisha |
Gajapati |
Nuagada |
Luhangar |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from RD road to Dasarathi sahi,Bagari |
68 days |
| 227 |
Odisha |
Gajapati |
Nuagada |
Parimala |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Bania sahi to VSS building, N.Baradang |
68 days |
| 228 |
Odisha |
Gajapati |
Nuagada |
Keradang |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from RD road to Shiv temple |
68 days |
| 229 |
Odisha |
Gajapati |
Nuagada |
Sambalpur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from RD road to Shiv temple |
68 days |
| 230 |
Odisha |
Gajapati |
Nuagada |
Paika Antarada |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from RD road to Mandala sahi,Guar |
68 days |
| 231 |
Odisha |
Gajapati |
Nuagada |
Paika Antarada |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Badasankha to Kusumpadara village |
68 days |
| 232 |
Odisha |
Gajapati |
Nuagada |
Tabarada |
Viplab Kumar Nayak |
Desk Officer |
Completion of incomplete bridge with approach road at K.Baradang |
68 days |
| 233 |
Odisha |
Gajapati |
Nuagada |
Kirama |
Viplab Kumar Nayak |
Desk Officer |
Construction of paver block road from RD road to Highschool |
68 days |
| 234 |
Odisha |
Gajapati |
Nuagada |
Badapada |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road from PWD road to Ambedkar Yuvaksangha community hall |
68 days |
| 235 |
Odisha |
Gajapati |
Nuagada |
Khajuripada |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from PWD road to DePaul School |
68 days |
| 236 |
Odisha |
Gajapati |
Nuagada |
Nuagada |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from PWD road to GPLF building Nuagada |
68 days |
| 237 |
Odisha |
Gajapati |
Nuagada |
Tangili |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from RD road to Smashan Ghat |
68 days |
| 238 |
Odisha |
Balasore |
Simulia |
Andarai |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Rasuna Chhak to swain sahi PMGSY road. |
68 days |
| 239 |
Odisha |
Balasore |
Simulia |
Anandapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC culvert near jagat upadhaya pokhari. |
68 days |
| 240 |
Odisha |
Balasore |
Simulia |
Bangalpur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from dhusasan jena house to nandi gadia. |
68 days |
| 241 |
Odisha |
Balasore |
Simulia |
Bangarkhandigadia |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road/drain with culvert at chhachinda village main road . |
68 days |
| 242 |
Odisha |
Balasore |
Simulia |
Bati |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from panda sahi to muduli sahi. |
68 days |
| 243 |
Odisha |
Balasore |
Simulia |
Jamujhadi |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Ganesh guru house to sura khilar with culvert. |
68 days |
| 244 |
Odisha |
Balasore |
Simulia |
Kanchapada |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from edatal minor to ganesh sahu house with culvert. |
68 days |
| 245 |
Odisha |
Balasore |
Simulia |
Kirkona |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from khirkona bala sahi to Uma ojha house. |
68 days |
| 246 |
Odisha |
Balasore |
Simulia |
Maitapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Markona Minor to CRC with culvert at badagahama. |
68 days |
| 247 |
Odisha |
Balasore |
Simulia |
Markona |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Mahaveer mandir to tala sahi. |
68 days |
| 248 |
Odisha |
Balasore |
Simulia |
Muruna |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Ratnakar house to chachanda with culvert. |
68 days |
| 249 |
Odisha |
Balasore |
Simulia |
Purosottampur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Balikhanda kanchapada RD road to Gouranga barik house. |
68 days |
| 250 |
Odisha |
Balasore |
Simulia |
Pahitorana |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Pratap pur minor to chaka Dinabandhu jena. |
68 days |
| 251 |
Odisha |
Balasore |
Simulia |
Samasundarpur |
Viplab Kumar Nayak |
Desk Officer |
Construction of Culvert at sadanandapur Mohanty sahi. |
68 days |
| 252 |
Odisha |
Gajapati |
R.Udayagiri |
Ramagiri |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from PWD road to Hatapada Ramagiri |
68 days |
| 253 |
Odisha |
Balasore |
Simulia |
Markona |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC Road from Arun padhi house to Adibashi sahi road. |
68 days |
| 254 |
Odisha |
Gajapati |
R.Udayagiri |
Anagha |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road at Baraba |
68 days |
| 255 |
Odisha |
Gajapati |
R.Udayagiri |
Ramagiri |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from RD road to Basundhara Over Head Tank Ramagiri |
68 days |
| 256 |
Odisha |
Gajapati |
R.Udayagiri |
Subalada |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road at Tobhajhola |
68 days |
| 257 |
Odisha |
Gajapati |
R.Udayagiri |
Mangarajpur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road at Nuasahi Tarapada |
68 days |
| 258 |
Odisha |
Gajapati |
R.Udayagiri |
Bastariguda |
Viplab Kumar Nayak |
Desk Officer |
Construction of Culvert at Kitung Nala A-Anjeikona |
68 days |
| 259 |
Odisha |
Gajapati |
Gosani |
Badakathuru |
Viplab Kumar Nayak |
Desk Officer |
Construction of paver block road at chatrapur |
68 days |
| 260 |
Odisha |
Gajapati |
Gosani |
Badagosani |
Viplab Kumar Nayak |
Desk Officer |
Construction of culvert near badabillo at mahadeipur |
68 days |
| 261 |
Odisha |
Gajapati |
Gosani |
Tatipetti |
Viplab Kumar Nayak |
Desk Officer |
Construction of road from gollagaon road to ghorani road |
68 days |
| 262 |
Odisha |
Gajapati |
Gosani |
Kerandi |
Viplab Kumar Nayak |
Desk Officer |
Construction of paver block road at indra nagar |
68 days |
| 263 |
Odisha |
Gajapati |
Gosani |
Kerandi |
Viplab Kumar Nayak |
Desk Officer |
Construction of culvert and drain sri ram bihar |
68 days |
| 264 |
Odisha |
Gajapati |
R.Udayagiri |
Ramagiri |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road at Goudasahi Ramagiri |
68 days |
| 265 |
Odisha |
Cuttack |
Tangi Choudwar |
Uchapada |
Viplab Kumar Nayak |
Desk Officer |
Imp of CC road from Narayana Baral house to Canal No-5 Sota, Khetrapal |
68 days |
| 266 |
Odisha |
Cuttack |
Tangi Choudwar |
Kotasahi |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of road from Bateswar to Koteswar, Kotasahi GP |
68 days |
| 267 |
Odisha |
Cuttack |
Tangi Choudwar |
Banipada |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road from Banipada AWC to Kambusagar Pokhari at Banipada |
68 days |
| 268 |
Odisha |
Cuttack |
Tangi Choudwar |
Banipada |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road from Rabi Mishra res. To Sudhir Parida res. At Gopalpur |
68 days |
| 269 |
Odisha |
Cuttack |
Tangi Choudwar |
Mangarajpur |
Viplab Kumar Nayak |
Desk Officer |
Const. of CC road from Mangal Melsandi house to forest road at Kochilanuagaon |
68 days |
| 270 |
Odisha |
Cuttack |
Tangi Choudwar |
Bramhapur |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road from Golakha Nayak house to Geda Tarai house,Jemadeipur |
68 days |
| 271 |
Odisha |
Cuttack |
Tangi Choudwar |
Kakhadi |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road from Kakhadi Bhagabata Sahi Naba Sahoo house to Achyuta Sahoo house |
68 days |
| 272 |
Odisha |
Cuttack |
Tangi Choudwar |
Garudagaon |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road from Fakir Sethy House Madan rout House |
68 days |
| 273 |
Odisha |
Cuttack |
Tangi Choudwar |
Jaripada |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road sanalekhanpur road & bridge |
68 days |
| 274 |
Odisha |
Cuttack |
Tangi Choudwar |
Bhatimunda |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road rameswar canal road , Saranga |
68 days |
| 275 |
Odisha |
Cuttack |
Tangi Choudwar |
Bhatimunda |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road Baniasahi cenal bridge |
68 days |
| 276 |
Odisha |
Cuttack |
Tangi Choudwar |
Napanga |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of CC road korkora pratapsahi to jora polo |
68 days |
| 277 |
Odisha |
Gajapati |
Mohona |
Sikulipadara |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Road from D. Colony to Talasing PWD Road |
68 days |
| 278 |
Odisha |
Gajapati |
Kasinagar |
Kidigam |
Viplab Kumar Nayak |
Desk Officer |
Construction of Culvert at Sunkanapeta Village |
68 days |
| 279 |
Odisha |
Gajapati |
Kasinagar |
Siali |
Viplab Kumar Nayak |
Desk Officer |
Construction from Karnibhadra Village to Nukalammma Mandir |
68 days |
| 280 |
Odisha |
Gajapati |
Kasinagar |
Parthada |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road at Sidhamasingh Street at T. Joduru |
68 days |
| 281 |
Odisha |
Gajapati |
Kasinagar |
K.Sitapur |
Viplab Kumar Nayak |
Desk Officer |
Improvement of Road at Bijalguda |
68 days |
| 282 |
Odisha |
Gajapati |
Kasinagar |
Allada |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road at Indira Colony(Bhaliaguda) |
68 days |
| 283 |
Odisha |
Gajapati |
Kasinagar |
K.Sitapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road at Nilakanthapur Street at Singipur Village |
68 days |
| 284 |
Odisha |
Gajapati |
Kasinagar |
K.Sitapur |
Viplab Kumar Nayak |
Desk Officer |
Construction of Paver Block road at D Tirupati House to G Khagi House Minigam |
68 days |
| 285 |
Odisha |
Gajapati |
Kasinagar |
Goribandha |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road at Trinath Mandap to Ram Mandir |
68 days |
| 286 |
Odisha |
Gajapati |
Kasinagar |
Budura |
Viplab Kumar Nayak |
Desk Officer |
Improvement of road from Market Complex Back side to towards tengalam Bothava Colony |
68 days |
| 287 |
Odisha |
Gajapati |
Mohona |
Antaraba |
Viplab Kumar Nayak |
Desk Officer |
Improvement road from PWD Road to Renu |
68 days |
| 288 |
Odisha |
Gajapati |
Mohona |
Garadama |
Viplab Kumar Nayak |
Desk Officer |
Improvement road from Gambhari school to RD road |
68 days |
| 289 |
Odisha |
Gajapati |
Mohona |
Mandimara |
Viplab Kumar Nayak |
Desk Officer |
Improvement road and culvert on the road to Saralapadar |
68 days |
| 290 |
Odisha |
Gajapati |
Mohona |
Gurujhuli |
Viplab Kumar Nayak |
Desk Officer |
Improvement road at RD Road to Gangudipankala |
68 days |
| 291 |
Odisha |
Gajapati |
Mohona |
Mohana |
Viplab Kumar Nayak |
Desk Officer |
Maintenance of Manikeswari Mandira road |
68 days |
| 292 |
Odisha |
Gajapati |
Mohona |
Manikapur |
Viplab Kumar Nayak |
Desk Officer |
Repair and Maintenance of Road from PWD road to hanuman temple Manikpur |
68 days |
| 293 |
Odisha |
Gajapati |
Mohona |
Birikote |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road at Patra sahi |
68 days |
| 294 |
Odisha |
Gajapati |
Mohona |
Luhagudi |
Viplab Kumar Nayak |
Desk Officer |
Construction of CC road at Main road to Odia sahi |
68 days |