Final Dpr

State: Odisha District: Ganjam Block: Chatrapur Gram Panchayat: Agastinuagam
Work Code: OD/354/3369/117673/412128/00056065 (CONSTRUCTION OF CC/PAVER ROAD AT WARD NO. 9 BACK SIDE FROM GOPAL SAHU TO PAKALU MASER HOUSE AT BADA NOLIANUAGAON)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Chatrapur Bill Status: Final Bill
Proposal Date: - Date of Commencement: 15-10-2025
Date of Completion: 19-10-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: ALOKNATH SETHI
Administrative Approval Details
Approval No.: OD/354/3369/117673/412128/00056065/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3369/117673/412128/00056065/TS
Fund Sanction No.: 14036
Fund Sanction Amount (in Rs.): 202038
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 17.24068368 5914.95678456 101977.89890347
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 13.061124 7469.97714172 97566.29772517
Total Amount (in Rs.): 199544.19662864
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled
Rs. 562 Rs. 462
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 17.24068368 Cubic Meter 3.9 67.238666352 0.18 3.1033230624
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.061124 Cubic Meter 4.6 60.0811704 0.68 8.88156432
Total Qty 11.9848873824 127.319836752
Rate Per Man Day 562 462
Total Amount 6735.5067089088 58821.764579424
Total Labour Amount (in Rs.): 65557.271288333
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 17.24068368 Cum 2.29 39.4811656272 0.48 8.2755281664 0.96 16.5510563328 - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.061124 Cum 3.23 42.18743052 0.45 5.8775058 - - 0.9 11.7550116
Total Qty 81.6685961472 14.1530339664 16.5510563328 11.7550116
Rate Per Unit 598.962 537.54 1401.46 1802.83
Total Amount 48916.385685519 7607.8218782987 23195.643408166 21192.287562828
Total Material Amount (in Rs.): 100912.13853481
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 17.24068368 Cum 2.29 39.4811656272 0.48 8.2755281664 0.96 16.5510563328 - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.061124 Cum 3.23 42.18743052 0.45 5.8775058 - - 0.9 11.7550116
Total Qty 81.6685961472 14.1530339664 16.5510563328 11.7550116
Rate Per Unit 0 774.25 252.5 252.5
Total Amount 0 10957.986548485 4179.141724032 2968.140429
Total Royalty Amount (in Rs.): 18105.268701517
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 498 Rs. 498
2 Contingency @ 1% Rs. 1995.4419662864
Total Addition Component Amount (in Rs.): 2493.4419662864
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ 1% Rs. 2020.3763859493
2 Royalty @ Rs. 4175.145020088 Rs. 4175.145020088
3 Additional Royalty @ Rs. 13303.851928416 Rs. 13303.851928416
4 EMF @ Rs. 208.7572510044 Rs. 208.7572510044
5 DMF @ Rs. 417.5145020088 Rs. 417.5145020088
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 85 x 3.945) @ 646.98 Rs. 646.98
7 Labour Cess @ 1% Rs. 2020.3763859493
Total Deduction Component Amount (in Rs.): 22793.001473416
Total Net Amount (in Rs.): 179244.63712151