Labour Statement

State: Odisha District: Balangir Block: Balangir Gram Panchayat: Chandanbhati
Work Code: OD/345/3285/115783/420044/00015160 (Const. of Facility Centre at GP Office, Chandanbhati)
Project Category: Building
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Balangir Bill Status: 1st Bill
Proposal Date: - Date of Commencement: 28-07-2025
Date of Completion: - Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Infrastructure for Banking Facilities at GP Hqrs Project Sub-Category: GP Facility Centre
Project Type: New Work Name of Executant:
Administrative Approval Details
Approval No.: OD/345/3285/115783/420044/00015160/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3285/115783/420044/00015160/TS
Fund Sanction No.: 343/ZP
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 512 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0122Aia) : Earthwork in all kinds of soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift - Earthwork in all kinds of soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge 26.860183808 Cubic Meter 0.5682408 15.263052335205 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 30.95945403328 Cubic Meter 0.1236 3.8265885185134 - - - - - -
3 R.C.C. Work (AR0404Aa) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) 23.19937232976 Cubic Meter 1.3333 30.931723127269 0.1323 3.0692769592272 0.175 4.059890157708 - -
4 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 19.8 Quintal 0.8 15.84 0.044 0.8712 - - 0.3 5.94
5 Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 24.93992532288 Cubic Meter 2.96 73.822178955725 - - 1.05 26.186921589024 0.35 8.728973863008
6 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 22.6643185904 Square Meter - - 0.6547619047619 14.839732410381 0.6547619047619 14.839732410381 - -
7 Concrete (AR0304) : Cement concrete (1:4:8) with 4 cm. hard granite(Crusher Broken) metal - Cement concrete (1:4:8) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 10.635241073882 Cubic Meter 3.9 41.47744018814 - - 0.18 1.9143433932988 - -
8 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 86.5421917184 Square Meter - - 0.30555555555556 26.443447469511 0.30555555555556 26.443447469511 - -
9 R.C.C. Work (AR0410e) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm 11.82004869 Square Meter - - 0.16025641025641 1.8942385721154 0.16025641025641 1.8942385721154 - -
10 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 27.52530084 Square Meter - - 0.05 1.376265042 0.05 1.376265042 - -
Total Qty 181.16098312485 76.714838634038 48.494160453235 14.668973863008
Rate Per Man Day 462 562 512 612
Total Amount 83696.374203682 43113.739312329 24829.010152056 8977.4120041609
Total Labour Amount (in Rs.): 160616.53567223