Labour Statement

State: Odisha District: Bhadrak Block: Dhamanagar Gram Panchayat: Bhaganpur
Work Code: OD/348/3327/116722/394651/00040292 (IMPROVEMENT OF ROAD AT MAA KALUNI THAKURANI PITHA ROAD)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Dhamanagar Bill Status: Final Bill
Proposal Date: 16-06-2025 Date of Commencement: 25-07-2025
Date of Completion: 15-09-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: DILLIP KUMAR PANDA
Administrative Approval Details
Approval No.: OD/348/3327/116722/394651/00040292/AS
Technical Sanction Details
Technical Sanction No.: OD/348/3327/116722/394651/00040292/TS
Fund Sanction No.: 15612
Fund Sanction Amount (in Rs.): 200001
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.7476 Cubic Meter 0.516 3.4817616 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 25.8367 Cubic Meter 0.1236 3.19341612 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 9.67156 Cubic Meter 3.9 37.719084 - - 0.18 1.7408808
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 41.584 Square Meter - - 0.05 2.0792 0.05 2.0792
Total Qty 44.39426172 3.8200808 2.0792
Rate Per Man Day 462 562 512
Total Amount 20510.14891464 2146.8854096 1064.5504
Total Labour Amount (in Rs.): 23721.58472424