Labour Statement

State: Odisha District: Ganjam Block: Surada Gram Panchayat: Badagada
Work Code: OD/354/3385/118019/411193/00049301 (Completion of incomplete awc badagada VI)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Surada Bill Status: 1st Bill
Proposal Date: 15-07-2025 Date of Commencement: 09-10-2025
Date of Completion: - Scheme Name: Asset Management Women and Child Development Department
Scheme Component Name: Self/Personal Deposit Project Sub-Category: AWC
Project Type: New Work Name of Executant: Monalisha Panda
Administrative Approval Details
Approval No.: OD/354/3385/118019/411193/00049301/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3385/118019/411193/00049301/TS
Fund Sanction No.: 4186
Fund Sanction Amount (in Rs.): 500000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 612 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 35.875120256 Cubic Meter 0.516 18.511562052096 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 24.00183221408 Cubic Meter 0.1236 2.9666264616603 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 10.618278121376 Cubic Meter 3.9 41.411284673366 - - 0.18 1.9112900618477 - -
4 Masonry Stone Work (AR0703) : Random rubble H.G. stone of masonry. - Random rubble H.G. stone of size not less than 0.0025 cum stacked masonry in cement mortar (1:6) in foundation and plinth including watering, curing for seven days with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 25.009610136 Cubic Meter 3.17 79.28046413112 - - 1.41 35.26355029176 0.35 8.7533635476
5 R.C.C. Work (AR0404Aa) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) 4.123917168 Cubic Meter 1.3333 5.4984187600944 0.1323 0.5455942413264 0.175 0.7216855044 - -
6 R.C.C. Work (AR0404Ab) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) 2.663354322 Cubic Meter 1.3333 3.5510503175226 0.3073 0.8184487831506 0.35 0.9321740127 - -
7 R.C.C. Work (AR0404Ac) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 1.3379688 Cubic Meter 1.3333 1.78391380104 5.29605 7.08594966324 5.33875 7.143080931 - -
8 Masonry Brick Work (AR0603ci) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 17.666922312 Cubic Meter 2.96 52.29409004352 - - 1.05 18.5502684276 0.35 6.1834228092
9 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 12.9854714 Quintal 0.8 10.38837712 0.044 0.5713607416 - - 0.3 3.89564142
10 R.C.C. Work (AR0404Ad) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) 1.775569548 Cubic Meter 1.3333 2.3673668783484 2.30105 4.0856743084254 2.34375 4.161491128125 - -
11 R.C.C. Work (AR0404Ag) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 0.343763686656 Cubic Meter 1.3333 0.45834012341844 3.11255 1.0699816629011 3.15525 1.0846603723213 - -
Total Qty 218.51149436219 69.768200729754 18.8324277768 14.177009400644
Rate Per Man Day 462 562 612 512
Total Amount 100952.31039533 39209.728810122 11525.445799402 7258.6288131295
Total Labour Amount (in Rs.): 158946.11381798