Labour Statement

State: Odisha District: Bargarh Block: Gaisilet Gram Panchayat: Katabahal
Work Code: OD/347/3317/116491/380101/00057086 (CONST OF CC ROAD AT KATABAHAL)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Gaisilet Bill Status: Final Bill
Proposal Date: - Date of Commencement: 09-10-2025
Date of Completion: 22-11-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Anuj Kumar Chandan
Administrative Approval Details
Approval No.: OD/347/3317/116491/380101/00057086/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3317/116491/380101/00057086/TS
Fund Sanction No.: 15615
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
Rs. 462 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 8.70625 Cubic Meter 0.516 4.492425 - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 25.84 Cubic Meter 0.1236 3.193824 - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 26.0925 Cubic Meter 3.9 101.76075 0.18 4.69665
4 Concrete (AR0307) : First floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 18.525 Cubic Meter 5.29 97.99725 0.782 14.48655
Total Qty 207.444249 19.1832
Rate Per Man Day 462 562
Total Amount 95839.243038 10780.9584
Total Labour Amount (in Rs.): 106620.201438