Labour Statement

State: Odisha District: Mayurbhanj Block: Samakhunta Gram Panchayat: Rangamatia
Work Code: OD/365/3506/120339/389102/00063179 (Const. of C.C. road from main road to Goura Singh house at Rangamatia)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Samakhunta Bill Status: Final Bill
Proposal Date: - Date of Commencement: 25-11-2025
Date of Completion: 11-12-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: SUSHANTA PANDUA
Administrative Approval Details
Approval No.: OD/365/3506/120339/389102/00063179/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3506/120339/389102/00063179/TS
Fund Sanction No.: 28365
Fund Sanction Amount (in Rs.): 297000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 20.39625 Cubic Meter 0.516 10.524465 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 15.40125 Cubic Meter 0.1236 1.9035945 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 21.9225 Cubic Meter 3.9 85.49775 - - 0.18 3.94605
4 Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.542 Cubic Meter 4.6 62.2932 - - 0.68 9.20856
5 R.C.C. Work (AR0410f) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor in ground floor R.C.C. walls and fins including attached pilasters 19.425 Square Meter - - 0.56485355648536 10.972280334728 0.56485355648536 10.972280334728
6 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 1.85 Square Meter - - 0.30555555555556 0.56527777777778 0.30555555555556 0.56527777777778
7 R.C.C. Work (AR0404B) : Reinforced cement concrete work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips.(Nominal mix as per IS-456, Table-9). - R.C.C. work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge(Nominal mix as per IS-456, Table-9). 0.33 Cubic Meter 1.3333 0.439989 0.0573 0.018909 0.1 0.033
Total Qty 160.6589985 24.725168112506 11.556467112506
Rate Per Man Day 462 562 512
Total Amount 74224.457307 13895.544479228 5916.911161603
Total Labour Amount (in Rs.): 94036.912947831