Labour Statement

State: Odisha District: Jagatsinghpur Block: Erasama Gram Panchayat: Nuadihi
Work Code: OD/355/3388/118109/397334/00064987 (Improvement of road from 13th C Canal Mahimadeipur Chhak to Madhuaganda Bridge)
Project Category: Road
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Erasama Bill Status: 1st Bill
Proposal Date: - Date of Commencement: 20-11-2025
Date of Completion: - Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: Susanta Kumar Nanda
Administrative Approval Details
Approval No.: OD/355/3388/118109/397334/00064987/AS
Technical Sanction Details
Technical Sanction No.: OD/355/3388/118109/397334/00064987/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 137025
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Semi-Skilled Skilled Un-Skilled
Rs. 512 Rs. 562 Rs. 462
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 10.4237166 Square Meter - - 0.05 0.52118583 0.05 0.52118583
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 15.1636464 Cubic Meter 4.6 69.75277344 - - 0.68 10.311279552
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 1.0831176 Cubic Meter 3.9 4.22415864 - - 0.18 0.194961168
Total Qty 0.52118583 11.02742655 73.97693208
Rate Per Man Day 512 562 462
Total Amount 266.84714496 6197.4137211 34177.34262096
Total Labour Amount (in Rs.): 40641.60348702