Labour Statement

State: Odisha District: Khordha Block: Begunia Gram Panchayat: Pangarasingh
Work Code: OD/362/3459/119590/407303/00065156 (IMPROVEMENT OF MUSLIM SAHI BACK SIDE ROAD)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Begunia Bill Status: Final Bill
Proposal Date: - Date of Commencement: 20-11-2025
Date of Completion: 23-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: All Weather Connectivity Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: ADITYA NARAYAN SINGH
Administrative Approval Details
Approval No.: OD/362/3459/119590/407303/00065156/AS
Technical Sanction Details
Technical Sanction No.: OD/362/3459/119590/407303/00065156/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 180048
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
Rs. 462 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 14.4 Cubic Meter 0.1236 1.77984 - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 16.2 Cubic Meter 3.9 63.18 0.18 2.916
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.2016 Cubic Meter 4.6 42.32736 0.68 6.257088
4 Earth Work (AR0101a) : Earthwork in ordinary soil within 50m, initial lead and 1.5m, initial lift - Earth work in ordinary soil within 50m, initial lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 1.8 Cubic Meter 0.32 0.576 - -
Total Qty 107.8632 9.173088
Rate Per Man Day 462 562
Total Amount 49832.7984 5155.275456
Total Labour Amount (in Rs.): 54988.073856