Labour Statement

State: Odisha District: Puri Block: Kakat Pur Gram Panchayat: Jaleswarpada
Work Code: OD/369/3540/120957/409171/00068055 (CONSTRUCTION AND REPAIR OF CHHELIBERUAN UP SCHOOL AT CHHELIBERUAN)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Kakat Pur Bill Status: Final Bill
Proposal Date: - Date of Commencement: 11-12-2025
Date of Completion: 22-12-2025 Scheme Name: Bikashita Gaon Bikashita Odisha
Scheme Component Name: Viksit Gaon Vikshit Odisha (VGVO) Project Sub-Category: Elementary School
Project Type: Upgradation or Improvement Name of Executant: PRACHI PRANGYA SAHOO AE
Administrative Approval Details
Approval No.: OD/369/3540/120957/409171/00068055/AS
Technical Sanction Details
Technical Sanction No.: OD/369/3540/120957/409171/00068055/TS
Fund Sanction No.: 6151
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Skilled
Rs. 462 Rs. 612 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 591.3268 Square Meter 0.11776344086022 69.63667864086 - - 0.10776344086022 63.72341064086
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.96985 Cubic Meter 4.6 55.06131 0.68 8.139498 - -
3 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 7.9799 Cubic Meter 0.1236 0.98631564 - - - -
4 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 15.9598 Cubic Meter 3.9 62.24322 0.18 2.872764 - -
Total Qty 187.92752428086 63.72341064086 11.012262
Rate Per Man Day 462 612 562
Total Amount 86822.516217757 38998.727312206 6188.891244
Total Labour Amount (in Rs.): 132010.13477396