Material Statement

State: Odisha District: Kendujhar Block: Bansapal Gram Panchayat: Kuanr
Work Code: OD/361/3444/119273/386317/00027551 (Maintenance Of Talapada Pry. School)
Project Category: Building
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Bansapal Bill Status: Final Bill
Proposal Date: - Date of Commencement: 20-09-2025
Date of Completion: 02-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance of Primary School Building Project Sub-Category: Elementary School
Project Type: Repair and Maintenance Name of Executant: RAJALAXMI SINGH
Administrative Approval Details
Approval No.: OD/361/3444/119273/386317/00027551/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3444/119273/386317/00027551/TS
Fund Sanction No.: 28923
Fund Sanction Amount (in Rs.): 250000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM132 BRM174 BRM340 BRM028 BRM131 BRMMR0027 BRM253 BRM142 BRM255 BRM029 BRM137 BRM141
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 62.2816044917 Sqm - - - - - - - - - - - - - - - - - - - - - - - -
2 Other Building Items. (AR1901Ba) :.Vitrified Tile 600mmx600mm Coloured /Printed - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Coloured /Printed series(Homogeneous) in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all work all materials, taxes, labor, T&P , etc. complete as per direction of Engineer-in-charge. 86.4489263967 Sqm 1 86.4489263967 0.0076 0.65701184061492 0.1074 9.2846146950056 0.021 1.8154274543307 - - - - - - - - - - - - - - - -
3 Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 5.0070629268 Sqm - - - - 0.1375 0.688471152435 0.015 0.075105943902 1 5.0070629268 1 5.0070629268 - - - - - - - - - - - -
4 Plastering (AR1027) :.6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 20.1002050807 Sqm - - - - 0.0372 0.74772762900204 0.0075 0.15075153810525 - - - - - - - - - - - - - - - -
5 Painting(AR0901dk) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface)(For repair and maintenance) . - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge(For repair and maintenance). 437.5419053017 Sqm - - - - - - - - - - - - 0.084 36.753520045343 - - - - - - - - - -
6 Painting(AR0901dik) :.Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces (outer surface )(For repair and maintenance) . - Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge(For repair and maintenance). 238.4624356282 Sqm - - - - - - - - - - - - 0.090322580645161 21.53854257287 - - - - - - - - - -
7 Painting(AR0922k) :.Finishing wall two coats with distemper of approved shades on new work (Inside)(For repair and maintenance). - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside)(For Repair and maintenance) 435.1032015517 Sqm - - - - - - - - - - - - - - 0.25 108.77580038793 - - - - - - - -
8 Painting(AR0918fk) :.Finishing wall with two coat weather coat paint of approved shade in the outer surface of old work(Outside)(For repair and maintenance) . - Finishing wall with two coat weather coat paint of approved shade in the outer surface of old work to give an even shade including all costs of labour, Paint and Brushes required for the work, etc. complete and as per direction of Engineer-in-charge(Outside)(For repair and maintenance). 228.2749527766 Sqm - - - - - - - - - - - - - - - - 0.125 28.534369097075 - - - - - -
9 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.00165587856 Cum - - - - - - - - - - - - - - - - - - 1 11.00165587856 - - - -
10 Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 69.410153875 Sqm - - - - - - - - - - - - - - - - - - - - 0.054 3.74814830925 0.125 8.676269234375
Total Qty 86.4489263967 0.65701184061492 10.720813476443 2.0412849363379 5.0070629268 5.0070629268 58.292062618212 108.77580038793 28.534369097075 11.00165587856 3.74814830925 8.676269234375
Rate Per Unit 713.5430561 2071.692 622.032 1570.91 668.8630561 8.5 159.57512 70.64512 195.33512 1008.91 143.24512 205.88512
Total Amount 61685.031137665 1361.1261741072 6668.6890483786 3206.6749193426 3349.0394113045 42.5600348778 9301.9628873488 7684.479471501 5573.7644117014 11099.680632438 536.90395433631 1786.3147324716
Total Material Amount (in Rs.): 112296.22681547