State: Odisha District: Balasore Block: Baleshwar Gram Panchayat: Bahabalpur
Work Code: OD/346/3299/116065/392004/00013873 (Const. of CC Road from Rangamatia Fisery Road to Jatindra Mandal house via- Rabindra Mandal house, Vill_ Rangamatia GP Bahabalpur.)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Baleshwar Proposal Date: 22-05-2023
Date of Commencement: 19-06-2025 Date of Completion: 22-07-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: ARUN KUMAR SWAIN
Administrative Approval Details
Approval No.: OD/346/3299/116065/392004/00013873/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3299/116065/392004/00013873/TS
Fund Sanction No.: 4907
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0101aa) : Earthwork in ordinary soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift - Earthwork in ordinary soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge per 100 cum 2.12376 Cubic Meter 0.384 0.81552384 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.565328 Cubic Meter 0.1236 2.0474745408 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.592064 Cubic Meter 3.9 53.0090496 - - 0.18 2.44657152
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.344544 Cubic Meter 4.6 42.9849024 - - 0.68 6.35428992
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 55.370188 Square Meter - - 0.05 2.7685094 0.05 2.7685094
Total Qty 98.8569503808 11.56937084 2.7685094
Rate Per Man Day 462 562 512
Total Amount 45671.91107593 6501.98641208 1417.4768128
Total Labour Amount (in Rs.): 53591.37430081