State: Odisha District: Kalahandi Block: Madanpur Rampur Gram Panchayat: M.Rampur
Work Code: OD/358/3419/118814/422708/00055148 (CONSTRUTION OF CC ROAD AND DRAIN FROM LALU BARIK GALI TO HARI HAR SAGAR, M.RAMPUR. CR NO- 11/23-24)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Madanpur Rampur Proposal Date: -
Date of Commencement: 22-09-2025 Date of Completion: 23-09-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: JE NAYAN
Administrative Approval Details
Approval No.: OD/358/3419/118814/422708/00055148/AS
Technical Sanction Details
Technical Sanction No.: OD/358/3419/118814/422708/00055148/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 8 Cubic Meter 0.1236 0.9888 - - - -
2 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 21.85 Cubic Meter 3.9 85.215 - - 0.18 3.933
3 R.C.C. Work (AR0403A) : Reinforced cement concrete work of M-15 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-15 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 10.95 Cubic Meter 1.33 14.5635 0.06 0.657 0.1 1.095
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 24 Square Meter - - 0.05 1.2 0.05 1.2
Total Qty 100.7673 6.228 1.857
Rate Per Man Day 462 562 512
Total Amount 46554.4926 3500.136 950.784
Total Labour Amount (in Rs.): 51005.4126