State: Odisha District: Nayagarh Block: Bhapur Gram Panchayat: Bijipur
Work Code: OD/367/3523/120594/406113/00055961 (Major Repairing of Door of Girls & Boys Toilet , Smart Class Roof grading, electrification of RCS High School, Bijipur)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Bhapur Proposal Date: -
Date of Commencement: 27-10-2025 Date of Completion: 11-01-2026
Scheme Name: Asset Management School and Mass Education Department Scheme Component Name: Self/Personal Deposit
Project Sub-Category: Secondary School Project Type: Repair and Maintenance
Name of Executant: Gayatri Khatua
Administrative Approval Details
Approval No.: OD/367/3523/120594/406113/00055961/AS
Technical Sanction Details
Technical Sanction No.: OD/367/3523/120594/406113/00055961/TS
Fund Sanction No.: 8559
Fund Sanction Amount (in Rs.): 150000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Semi-Skilled Skilled
462 612 512 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Dismantling (AR1621) : First floor - Removing old grading plaster from roof slab, cleaning the surface,lowering and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 197.87 Square Meter 0.175 34.62725 - - - - - -
2 Concrete (AR0317) : First floor - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 197.87 Square Meter 0.414 81.91818 - - - - 0.115 22.75505
3 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 2.205 Quintal 6.3976377952756 14.106791338583 1.9685039370079 4.3405511811024 3.9370078740157 8.6811023622047 3.4448818897638 7.5959645669291
Total Qty 130.65222133858 30.351014566929 4.3405511811024 8.6811023622047
Rate Per Man Day 462 612 512 562
Total Amount 60361.326258425 18574.820914961 2222.3622047244 4878.7795275591
Total Labour Amount (in Rs.): 86037.288905669