State: Odisha District: Jagatsinghpur Block: Balikuda Gram Panchayat: Arilo
Work Code: OD/355/3386/118047/398250/00057078 (Construction of CC road from Netapur Godadia to Kolathapatan )
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Balikuda Proposal Date: -
Date of Commencement: 24-10-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: SANJAY KUMAR KALLO
Administrative Approval Details
Approval No.: OD/355/3386/118047/398250/00057078/AS
Technical Sanction Details
Technical Sanction No.: OD/355/3386/118047/398250/00057078/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 700000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0110) :.Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. 373.7775 Sqm - - - - - - - - - - - - - -
2 Earth Work (AR0101aa) :.Earthwork in ordinary soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift - Earthwork in ordinary soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge per 100 cum 12.255 Cum - - - - - - - - - - - - - -
3 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 23.4376875 Cum 1 23.4376875 - - - - - - - - - - - -
4 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 49.63275 Cum - - 2.29 113.6589975 0.48 23.82372 0.96 47.64744 - - - - - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 37.37775 Cum - - 3.23 120.7301325 0.45 16.8199875 - - 0.9 33.639975 - - - -
6 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 49.02 Sqm - - - - - - - - - - 0.00267 0.1308834 0.126 6.17652
Total Qty 23.4376875 234.38913 40.6437075 47.64744 33.639975 0.1308834 6.17652
Rate Per Unit 599.61 613.327 608.12 2418.36 2819.73 58573.086 229.106
Total Amount 14053.471801875 143757.18193551 24716.2514049 115228.6629984 94855.64670675 7666.2446441724 1415.07779112
Total Material Amount (in Rs.): 401692.53728273